Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Kandy - Central Province
Kundasale
Jayasinghe Construction (Pvt) Ltd
Timeline
-
182 days - 2026-04-30 -> 2026-10-28
Scheduled Completion
2026-10-28
257,721,453.96 LKR
RDA/DRP/CEN/KDY/KUN/21
46,231,491.42 LKR excl. VAT
17.9% of contract
31 days left
150 / 182 days • 2026-04-30 -> 2026-10-28
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.2
Tender ByRM&M
Scope
Contract NameImprovement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Estimated Road Lengths- km
Number of Roads0
Scope SummarySurface Overlaying and Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/21
Tender Batch No.4
Contractor NameJayasinghe Construction (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount257,721,453.96
Engineer Estimate Amount (LKR)314,486,807.16
Duration (Days)182
CategoryEmergency
Document Readiness
7 of 12 required documents received.
7 Received
5 Pending
Contractual
6/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
Yes
Advance Bond
Yes
Technical
1/5
Source Approval Request
Yes
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-10-28
Duration Elapsed
150 / 182 days
Schedule Status
On schedule - 31 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress11.5% vs 87.3%
Financial Progress17.9% vs 74.5%
Overall Progress
Overall
Planned: 87.3%
Behind by 75.8%
Financial Actual: 46.23 Mn / Planned 192.00 Mn
Behind 145.77 Mn
Critical Issues
In the process of Termination
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.2% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
IPC 2 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 17.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 3 as IPC.
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Kandy - Kundasale
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Project Name:
Project #21 - Contract No. RDA/DRP/CEN/KDY/KUN/21
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/KDY/KUN/21
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 11.5%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
Project Name:
Project #21 - Contract No. RDA/DRP/CEN/KDY/KUN/21
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/KDY/KUN/21
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 46.23 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
30 Apr 2026
Today - 27 Sep 2026
28 Oct 2026
11.5% actual
82.9% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+0.4% / week
Estimated completion
2030-09-09
Weeks to 100%
203.5
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
11.5%
Current progress
11.5%
Change
+0.5%
Project Notes
0
No notes yet. Add the first note to start the conversation.