Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km
Kandy - Central Province
Gampola
Weebadda Construction
Timeline
-
105 days - — -> —
22,481,370.00 LKR
RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
— LKR excl. VAT
0% of contract
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionGampola
Package No.-
Tender ByPD(CP)
Scope
Contract NameConstruction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Tender Batch No.-
Contractor NameWeebadda Construction
Consultant-
Tender StatusAwarded
LOA Date2026-09-14
Contract Amount22,481,370.00
Engineer Estimate Amount (LKR)26,379,398.72
Duration (Days)105
CategoryPD(CP)
Document Readiness
0 of 12 required documents received.
0 Received
12 Pending
Contractual
0/7
LOA Issued
—
Agreement Signed
—
Escrow Agreement
—
Performance Bond
—
Contract Doc. Received
—
Insurance
—
Advance Bond
—
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Duration Elapsed
0 / 105 days
Schedule Status
-
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress0% vs 0%
Financial Progress0% vs 0%
Overall Progress
Overall
Planned: 0%
Ahead by 0%
Financial Actual: 0.00 Mn / Planned 0.00 Mn
Ahead 0.00 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
0%
Planned vs Actual Curve
Set the Commenced Date & Duration (Days) to generate the planned curve.
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
No Advance IPC yet. Click Add Advance IPC to create IPC 1 as Advance.
0/20 used - next: IPC 1 as Advance
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 1 as IPC.
0/20 used - next: IPC 1 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
Amount-
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
Amount-
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
Amount-
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Kandy - Gampola
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km
Project Name:
Project #129 - Contract No. RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 17:19
Contract No. RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 0%
Set Commenced Date & Duration to generate the physical planned curve.
Go to Mobilization & Contract Period to set dates.
No physical schedule yet - set Commenced Date & Duration to generate.
Presentage
Actual financial
Kandy - Gampola
Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km
Project Name:
Project #129 - Contract No. RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 17:19
Contract No. RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 0.00 Mn
Set Commenced Date & Duration to generate the financial planned curve.
No financial schedule yet - set Commenced Date & Duration to generate.
Project Timeline
On track
Set Commenced Date & Scheduled Completion to view the timeline.
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot
2026-09-24
Snapshot value
0%
Current progress
0%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.