Ditwah (CP) Awarded

RDA/DRP/CEN/KDY/KUN/25

Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)

Kandy - Central Province Kundasale S N O Builders (Pvt) Ltd
Progress -41.9% vs plan
36%
Complete
Planned77.9%
Time69.7%
35 days left - 83/119d
Timeline
LOA
2026-06-16
Possession
2026-07-06
Commencement
2026-07-06
Scheduled Completion
2026-11-01
Original Contract

157,909,825.01 LKR

RDA/DRP/CEN/KDY/KUN/25

Total Certified

36,169,281.06 LKR excl. VAT

22.9% of contract

Overall Progress

36%

-41.9% vs planned
Plan 77.9%
Schedule

35 days left

69.7% time

83 / 119 days • 2026-07-06 -> 2026-11-01

Swipe tabs to see all sections — tap to switch

Planned

77.9%

Actual

36%

Presentage

-41.9%

Time Elapsed

69.7%

Days Left

35

Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.6
Tender By-
Scope
Contract NameConstruction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Gabion Retaining Wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/25
Tender Batch No.12
Contractor NameS N O Builders (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-06-16
Contract Amount157,909,825.01
Engineer Estimate Amount (LKR)178,738,774.63
Duration (Days)119
CategoryEmergency