Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Kandy - Central Province
Kundasale
S N O Builders (Pvt) Ltd
Timeline
-
119 days - 2026-07-06 -> 2026-11-01
Scheduled Completion
2026-11-01
157,909,825.01 LKR
RDA/DRP/CEN/KDY/KUN/25
36,169,281.06 LKR excl. VAT
22.9% of contract
35 days left
83 / 119 days • 2026-07-06 -> 2026-11-01
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.6
Tender By-
Scope
Contract NameConstruction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Gabion Retaining Wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/25
Tender Batch No.12
Contractor NameS N O Builders (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-06-16
Contract Amount157,909,825.01
Engineer Estimate Amount (LKR)178,738,774.63
Duration (Days)119
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-11-01
Duration Elapsed
83 / 119 days
Schedule Status
On schedule - 35 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress36% vs 77.9%
Financial Progress22.9% vs 55.9%
Overall Progress
Overall
Planned: 77.9%
Behind by 41.9%
Financial Actual: 36.17 Mn / Planned 88.27 Mn
Behind 52.10 Mn
Critical Issues
NOT YET MOBILIZED
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.2% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 22.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Kandy - Kundasale
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Project Name:
Project #25 - Contract No. RDA/DRP/CEN/KDY/KUN/25
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/KDY/KUN/25
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 36%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Project Name:
Project #25 - Contract No. RDA/DRP/CEN/KDY/KUN/25
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/KDY/KUN/25
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 36.17 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
06 Jul 2026
Today - 27 Sep 2026
01 Nov 2026
36% actual
70.3% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+2.7% / week
Estimated completion
2027-03-15
Weeks to 100%
23.7
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
36%
Current progress
36%
Change
+6%
Project Notes
0
No notes yet. Add the first note to start the conversation.