Ditwah (CP) Awarded

RDA/DRP/CEN/MTL/NAL/48R

Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)

Matale - Central Province Nalanda S A P Engineering (Pvt) Ltd
Progress +0% vs plan
0%
Complete
Planned0%
Time0%
- - 0/154d
Timeline
LOA
2026-08-31
Possession
-
Commencement
-
Scheduled Completion
-
Original Contract

50,471,466.08 LKR

RDA/DRP/CEN/MTL/NAL/48R

Total Certified

— LKR excl. VAT

0% of contract

Overall Progress

0%

+0% vs planned
Plan 0%
Schedule

-

0% time

0 / 154 days • — -> —

Swipe tabs to see all sections — tap to switch

Planned

0%

Actual

0%

Presentage

+0%

Time Elapsed

0%

Days Left

-

Location & Package
ProvinceCentral Province
DistrictMatale
EE DivisionNalanda
Package No.6
Tender By-
Scope
Contract NameRehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Estimated Road Lengths- km
Number of Roads0
Scope SummarySurfacing (Asphalt) , hard shoulder, shoulder, drain construction
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/NAL/48R
Tender Batch No.11
Contractor NameS A P Engineering (Pvt) Ltd
ConsultantNalanda EE
Tender StatusAwarded
LOA Date2026-08-31
Contract Amount50,471,466.08
Engineer Estimate Amount (LKR)42,736,925.80
Duration (Days)154
CategoryEmergency