Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
Matale - Central Province
Nalanda
Platinum Holdings Lanka (Private) Limited
Timeline
-
119 days - 2026-06-18 -> 2026-10-14
Scheduled Completion
2026-10-14
17,458,592.78 LKR
RDA/DRP/CEN/MTL/NAL/51
4,782,609.49 LKR excl. VAT
27.4% of contract
17 days left
101 / 119 days • 2026-06-18 -> 2026-10-14
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictMatale
EE DivisionNalanda
Package No.9
Tender By-
Scope
Contract NameRehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryRetaning wall ,Drain and shoulder Constructions
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/NAL/51
Tender Batch No.11
Contractor NamePlatinum Holdings Lanka (Private) Limited
ConsultantNalanda EE
Tender StatusAwarded
LOA Date2026-05-29
Contract Amount17,458,592.78
Engineer Estimate Amount (LKR)25,992,198.15
Duration (Days)119
CategoryEmergency
Document Readiness
6 of 12 required documents received.
6 Received
6 Pending
Contractual
6/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
Yes
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-10-14
Duration Elapsed
101 / 119 days
Schedule Status
17 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress68% vs 89.3%
Financial Progress27.4% vs 78.6%
Overall Progress
Overall
Planned: 89.3%
Behind by 21.3%
Financial Actual: 4.78 Mn / Planned 13.72 Mn
Behind 8.94 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 18.3% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 27.4% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Matale - Nalanda
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
Project Name:
Project #51 - Contract No. RDA/DRP/CEN/MTL/NAL/51
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/MTL/NAL/51
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 68%
Weekly Planned (Physical %)
Presentage
Actual financial
Matale - Nalanda
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
Project Name:
Project #51 - Contract No. RDA/DRP/CEN/MTL/NAL/51
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/MTL/NAL/51
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 4.78 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
18 Jun 2026
Today - 27 Sep 2026
14 Oct 2026
68% actual
85.6% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+3.8% / week
Estimated completion
2026-11-12
Weeks to 100%
8.5
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
68%
Current progress
68%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.