Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
Kandy - Central Province
Kandy
Jayawansa Construction (Pvt) Ltd
Timeline
-
182 days - 2026-09-09 -> 2027-03-09
Scheduled Completion
2027-03-09
79,071,437.68 LKR
RDA/DRP/CEN/KDY/KDY/15
— LKR excl. VAT
0% of contract
163 days left
18 / 182 days • 2026-09-09 -> 2027-03-09
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKandy
Package No.3
Tender By-
Scope
Contract NameRehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Retaining structures, Construction of Gabian wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KDY/15
Tender Batch No.-
Contractor NameJayawansa Construction (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-08-14
Contract Amount79,071,437.68
Engineer Estimate Amount (LKR)79,953,569.86
Duration (Days)182
CategoryEmergency
Document Readiness
1 of 12 required documents received.
1 Received
11 Pending
Contractual
1/7
LOA Issued
Yes
Agreement Signed
—
Escrow Agreement
—
Performance Bond
—
Contract Doc. Received
—
Insurance
—
Advance Bond
—
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2027-03-09
Duration Elapsed
18 / 182 days
Schedule Status
On schedule - 163 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress3.5% vs 7.9%
Financial Progress0% vs 3.2%
Overall Progress
Overall
Planned: 7.9%
Behind by 4.4%
Financial Actual: 0.00 Mn / Planned 2.53 Mn
Behind 2.53 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
No Advance IPC yet. Click Add Advance IPC to create IPC 1 as Advance.
0/20 used - next: IPC 1 as Advance
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 1 as IPC.
0/20 used - next: IPC 1 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Kandy - Kandy
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
Project Name:
Project #15 - Contract No. RDA/DRP/CEN/KDY/KDY/15
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/KDY/KDY/15
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 3.5%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kandy
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
Project Name:
Project #15 - Contract No. RDA/DRP/CEN/KDY/KDY/15
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/KDY/KDY/15
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
09 Sep 2026
Today - 27 Sep 2026
09 Mar 2027
3.5% actual
9.9% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+1.3% / week
Estimated completion
2028-03-13
Weeks to 100%
75.9
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
3.5%
Current progress
3.5%
Change
+3.5%
Project Notes
0
No notes yet. Add the first note to start the conversation.