Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
Kandy - Central Province
Kundasale
S N O Builders (Pvt) Ltd
Timeline
-
182 days - 2026-07-06 -> 2027-01-03
Scheduled Completion
2027-01-03
91,559,621.04 LKR
RDA/DRP/CEN/KDY/KUN/29
22,101,802.05 LKR excl. VAT
24.1% of contract
98 days left
83 / 182 days • 2026-07-06 -> 2027-01-03
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.10
Tender By-
Scope
Contract NameImprovement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Retaining Walls, "U" Drain and Shoulder Construction
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/29
Tender Batch No.12
Contractor NameS N O Builders (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-06-16
Contract Amount91,559,621.04
Engineer Estimate Amount (LKR)100,543,979.99
Duration (Days)182
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2027-01-03
Duration Elapsed
83 / 182 days
Schedule Status
On schedule - 98 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress39% vs 44.2%
Financial Progress24.1% vs 25.4%
Overall Progress
Overall
Planned: 44.2%
Behind by 5.2%
Financial Actual: 22.10 Mn / Planned 23.26 Mn
Behind 1.16 Mn
Critical Issues
NOT YET MOBILIZED
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.8% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 2 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 24.1% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 3 (IPC)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 2 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Kandy - Kundasale
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
Project Name:
Project #29 - Contract No. RDA/DRP/CEN/KDY/KUN/29
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/KDY/KUN/29
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 39%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
Project Name:
Project #29 - Contract No. RDA/DRP/CEN/KDY/KUN/29
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/KDY/KUN/29
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 22.10 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
06 Jul 2026
Today - 27 Sep 2026
03 Jan 2027
39% actual
45.9% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+3% / week
Estimated completion
2027-02-27
Weeks to 100%
20.5
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
39%
Current progress
39%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.