Contract No.

RDA/DRP/CEN/MTL/NAL/49

Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- Elahera- Pallegama- Hettipola Road (B-312…

Matale Nalanda Naula- Elahera-Pallegama-Hettipola Road … Awarded Progress 42%
Original Contract Amount

44,706,119.13

Revised Estimate

56,512,677.41

Total Certified to Date

Overall Progress
42%
Project Information
Contract No.RDA/DRP/CEN/MTL/NAL/49
S/N49
Serial No.124
ProvinceCentral
DistrictMatale
Implementing AgencyNalanda
Package No.7
Tender ByRM&M
Road NameNaula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+24…
Contract DescriptionRehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- E…
Estimated Road Lengths0.00 km
Number of Roads0
Number of Structures
Chainage8+200 - 61+240
Scope SummaryShoulder work .Drains & Cash barrier
Scope & Duration
Commenced Date2026-06-18
Scheduled Completion2026-11-18
Possession of Site
Contractor & Award
Contractor NamePlatinum Holdings Lanka (Private) Limited
Tender StatusAwarded
LOA Date2026-05-29
Contract Amount44,706,119.13
Estimate Amount56,512,677.41
Duration (Days)154
Tender Batch No.11