Ditwah (CP) Awarded

RDA/DRP/CEN/NUE/HAN/57

Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )

NuwaraEliya - Central Province Hanguranketha Samindra Construction
Progress -62.8% vs plan
10%
Complete
Planned72.8%
Time64.8%
31 days left - 59/91d
Timeline
LOA
2026-07-09
Possession
2026-07-30
Commencement
2026-07-30
Scheduled Completion
2026-10-28
Original Contract

47,755,538.96 LKR

RDA/DRP/CEN/NUE/HAN/57

Total Certified

— LKR excl. VAT

0% of contract

Overall Progress

10%

-62.8% vs planned
Plan 72.8%
Schedule

31 days left

64.8% time

59 / 91 days • 2026-07-30 -> 2026-10-28

Swipe tabs to see all sections — tap to switch

Planned

72.8%

Actual

10%

Presentage

-62.8%

Time Elapsed

64.8%

Days Left

31

Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionHanguranketha
Package No.7
Tender By-
Scope
Contract NameRehabilitation / Improvement of Keerthibandarapura Naranthalawa Road
( B -511 ) ( 0+000 - 4+100 )
Estimated Road Lengths- km
Number of Roads0
Scope SummarySurfacing(Asphalt), Drain,Shoulder,Hard shoulder,Retaning wall Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/HAN/57
Tender Batch No.12
Contractor NameSamindra Construction
ConsultantHanguranketha EE
Tender StatusAwarded
LOA Date2026-07-09
Contract Amount47,755,538.96
Engineer Estimate Amount (LKR)44,694,533.62
Duration (Days)91
CategoryEmergency