Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
NuwaraEliya - Central Province
NuwaraEliya
KSJ Construction (Pvt) Ltd
Timeline
-
91 days - 2026-05-02 -> 2026-07-31
Overdue 58d
Scheduled Completion
2026-07-31
161,841,095.70 LKR
RDA/DRP/CEN/NUE/NUE/66
43,581,397.85 LKR excl. VAT
26.9% of contract
58d overdue
148 / 91 days • 2026-05-02 -> 2026-07-31
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNuwaraEliya
Package No.7
Tender ByRM&M
Scope
Contract NameRehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
Estimated Road Lengths- km
Number of Roads0
Scope SummaryRoad Marking, U Drain Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/66
Tender Batch No.3
Contractor NameKSJ Construction (Pvt) Ltd
ConsultantNuwara Eliya EE
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount161,841,095.70
Engineer Estimate Amount (LKR)205,630,098.81
Duration (Days)91
CategoryEmergency
Document Readiness
6 of 12 required documents received.
6 Received
6 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
1/5
Source Approval Request
Yes
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-07-31
Duration Elapsed
148 / 91 days
Schedule Status
Overdue by 58 days
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress60% vs 100%
Financial Progress26.9% vs 100%
Overall Progress
Overall
Planned: 100%
Behind by 40%
Financial Actual: 43.58 Mn / Planned 161.84 Mn
Behind 118.26 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
50%
Drainage Construction
30%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.1% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 26.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 58d overdue
NuwaraEliya - NuwaraEliya
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
Project Name:
Project #66 - Contract No. RDA/DRP/CEN/NUE/NUE/66
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/NUE/NUE/66
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 60%
Weekly Planned (Physical %)
Presentage
Actual financial
NuwaraEliya - NuwaraEliya
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
Project Name:
Project #66 - Contract No. RDA/DRP/CEN/NUE/NUE/66
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/NUE/NUE/66
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 43.58 Mn
Weekly Planned (Financial Mn)
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
60% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+2.8% / week
Estimated completion
2026-12-29
Weeks to 100%
14.3
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
60%
Current progress
60%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.