Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Matale - Central Province
Matale
Lahiru Construction and Consultants (Pvt) Ltd
Timeline
-
182 days - 2026-05-02 -> 2026-10-30
Scheduled Completion
2026-10-30
292,279,354.08 LKR
RDA/DRP/CEN/MTL/MTL/32
61,223,368.41 LKR excl. VAT
20.9% of contract
33 days left
148 / 182 days • 2026-05-02 -> 2026-10-30
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictMatale
EE DivisionMatale
Package No.2
Tender By-
Scope
Contract NameRehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Estimated Road Lengths- km
Number of Roads0
Scope SummaryShoulder and embankment constructions, surface applications, construction of drainage structures and construction of retaining structures
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/32
Tender Batch No.3
Contractor NameLahiru Construction and Consultants (Pvt) Ltd
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount292,279,354.08
Engineer Estimate Amount (LKR)395,635,536.56
Duration (Days)182
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-10-30
Duration Elapsed
148 / 182 days
Schedule Status
On schedule - 33 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress64% vs 86.4%
Financial Progress19.5% vs 72.8%
Overall Progress
Overall
Planned: 86.4%
Behind by 22.4%
Financial Actual: 56.91 Mn / Planned 212.78 Mn
Behind 155.87 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
30%
Drainage Construction
50%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.2% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
3/20 used - next: IPC 4 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 19.5% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
IPC 3 (IPC)
PD Certified
Swipe to see all certificate stages
3/20 used - next: IPC 4 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Matale - Matale
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Project Name:
Project #32 - Contract No. RDA/DRP/CEN/MTL/MTL/32
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/MTL/MTL/32
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 64%
Weekly Planned (Physical %)
Presentage
Actual financial
Matale - Matale
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Project Name:
Project #32 - Contract No. RDA/DRP/CEN/MTL/MTL/32
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/MTL/MTL/32
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 56.91 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
64% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+0.9% / week
Estimated completion
2027-06-29
Weeks to 100%
39.2
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
64%
Current progress
64%
Change
+1%
Project Notes
0
No notes yet. Add the first note to start the conversation.