Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
NuwaraEliya - Central Province
-
Southern group civil construction (Pvt) Ltd
Timeline
-
182 days - 2026-05-02 -> 2026-10-30
Scheduled Completion
2026-10-30
266,045,892.19 LKR
RDA/DRP/CEN/NUE/NUE/69
80,907,797.95 LKR excl. VAT
30.4% of contract
33 days left
148 / 182 days • 2026-05-02 -> 2026-10-30
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE Division-
Package No.10
Tender By-
Scope
Contract NameRehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryRoad Marking Retaining wall Construction, Edge Wedining, Drain Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/69
Tender Batch No.4
Contractor NameSouthern group civil construction (Pvt) Ltd
ConsultantNuwara Eliya EE
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount266,045,892.19
Engineer Estimate Amount (LKR)365,868,062.33
Duration (Days)182
CategoryEmergency
Document Readiness
7 of 12 required documents received.
7 Received
5 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
2/5
Source Approval Request
Yes
Drawings Submitted
Yes
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-10-30
Duration Elapsed
148 / 182 days
Schedule Status
On schedule - 33 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress47% vs 86.4%
Financial Progress28.9% vs 72.8%
Overall Progress
Overall
Planned: 86.4%
Behind by 39.4%
Financial Actual: 76.94 Mn / Planned 193.68 Mn
Behind 116.74 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
20%
Drainage Construction
45%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.9% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
4/20 used - next: IPC 5 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 28.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
IPC 3 (IPC)
Paid
Swipe to see all certificate stages
IPC 4 (IPC)
PD Certified
Swipe to see all certificate stages
4/20 used - next: IPC 5 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
NuwaraEliya - -
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Project Name:
Project #69 - Contract No. RDA/DRP/CEN/NUE/NUE/69
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/NUE/NUE/69
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 47%
Weekly Planned (Physical %)
Presentage
Actual financial
NuwaraEliya - -
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Project Name:
Project #69 - Contract No. RDA/DRP/CEN/NUE/NUE/69
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:27
Contract No. RDA/DRP/CEN/NUE/NUE/69
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 76.94 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
47% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+2.3% / week
Estimated completion
2027-02-21
Weeks to 100%
23.2
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
47%
Current progress
47%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.