Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)
NuwaraEliya - Central Province
-
KSJ Construction (Pvt) Ltd
Timeline
-
182 days - 2026-05-02 -> 2026-10-30
Scheduled Completion
2026-10-30
239,417,811.34 LKR
RDA/DRP/CEN/NUE/NUE/67
79,089,759.22 LKR excl. VAT
33% of contract
33 days left
148 / 182 days • 2026-05-02 -> 2026-10-30
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE Division-
Package No.8
Tender By-
Scope
Contract NameRehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryRoad Marking, U Drain Construction ,Shoulder Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/67
Tender Batch No.3
Contractor NameKSJ Construction (Pvt) Ltd
ConsultantNuwara Eliya EE
Tender StatusAwarded
LOA Date2026-03-17
Contract Amount239,417,811.34
Engineer Estimate Amount (LKR)302,933,613.60
Duration (Days)182
CategoryEmergency
Document Readiness
6 of 12 required documents received.
6 Received
6 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
1/5
Source Approval Request
Yes
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-10-30
Duration Elapsed
148 / 182 days
Schedule Status
On schedule - 33 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress70% vs 86.4%
Financial Progress27.7% vs 72.8%
Overall Progress
Overall
Planned: 86.4%
Behind by 16.4%
Financial Actual: 66.24 Mn / Planned 174.30 Mn
Behind 108.06 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
30%
Drainage Construction
40%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.3% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
3/20 used - next: IPC 4 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 27.7% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
Paid
Swipe to see all certificate stages
IPC 3 (IPC)
PD Certified
Swipe to see all certificate stages
3/20 used - next: IPC 4 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
NuwaraEliya - -
Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)
Project Name:
Project #67 - Contract No. RDA/DRP/CEN/NUE/NUE/67
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/NUE/NUE/67
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 70%
Weekly Planned (Physical %)
Presentage
Actual financial
NuwaraEliya - -
Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)
Project Name:
Project #67 - Contract No. RDA/DRP/CEN/NUE/NUE/67
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/NUE/NUE/67
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 66.24 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
70% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+3.3% / week
Estimated completion
2026-11-23
Weeks to 100%
9.1
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
70%
Current progress
70%
Change
+0%
Project Notes
0
No notes yet. Add the first note to start the conversation.