Ditwah (CP) Pending

RDA/DC/DRP/SLOPE/PD(CP)/NE/NOR/14

Construction of Slope failure mitigation measures along Avissawella-Hatton-Nuwaraeliya Road (A007) (Culvert No 71/1 to Ch 70+000 km)

NuwaraEliya - Central Province Norwood -
Progress +0% vs plan
0%
Complete
Planned0%
Time0%
- - 0/0d
Timeline
LOA
-
Possession
-
Commencement
-
Scheduled Completion
-
Original Contract

— LKR

RDA/DC/DRP/SLOPE/PD(CP)/NE/NOR/14

Total Certified

— LKR excl. VAT

-

Overall Progress

0%

+0% vs planned
Plan 0%
Schedule

-

0% time

0 / 0 days • — -> —

Swipe tabs to see all sections — tap to switch

Planned

0%

Actual

0%

Presentage

+0%

Time Elapsed

0%

Days Left

-

Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNorwood
Package No.-
Tender By
Scope
Contract NameConstruction of Slope failure mitigation measures along Avissawella-Hatton-Nuwaraeliya Road (A007) (Culvert No 71/1 to Ch 70+000 km)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/PD(CP)/NE/NOR/14
Tender Batch No.-
Contractor Name-
Consultant-
Tender StatusPending
LOA Date—
Contract Amount—
Engineer Estimate Amount (LKR)29,300,952.07
Duration (Days)-
CategoryPD(CP)