DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 17 awarded projects

2026-11-04
22:36:41Live2026-11-04
0 / 17Advance Pendingpending advance projects / total projects
0 / 17IPC Pendingpending IPC projects / total projects
0 / 17Advance Paidadvance paid projects / total projects
0 / 17IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Batticaloa · EE: Batticaloa · EE Office

17Projects405.9Contract Mn
Batticaloa 17 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Below 50Mn15339.568.520% of contract271.0——————46.7%0.0%
DL Stage 01132.432.199% of contract0.3——————100.0%0.0%
DL Stage 02133.924.572% of contract9.4——————100.0%0.0%
Batticaloa17405.9125.131% of contract280.8000.0000.053.0%0.0%
Tender Below 50Mn15 projects339.5Mn
20% paid68.5 Mn
Pending271.0Mn
Planned Fin46.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project32.4Mn
99% paid32.1 Mn
Pending0.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project33.9Mn
72% paid24.5 Mn
Pending9.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Batticaloa17 projects405.9Mn
31% paid125.1 Mn
Pending280.8Mn
Planned Fin53.0%
Actual Fin0.0%

Avg Physical Progress per Province · Batticaloa · EE: Batticaloa

Project-wise Financials · Batticaloa · EE: Batticaloa (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Batticaloa · EE: Batticaloa (Mn · incl. VAT)

Scroll horizontally — 579 projects

Batticaloa Division · Batticaloa · EE: Batticaloa (Mn · incl. VAT)

Batticaloa District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:17 awarded · Batticaloa · EE: Batticaloa
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

531–540/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
531RR/RDA/25/08/11
Thambagala Margaya Sanwardanaya Kirima (Highway pitawime sthanayen arambha vi Pr…
—
9,396,645.17————————————
532RR/RDA/09/25/02
Wam Iwura Janawasa Margaya
—
37,666,563.49————————————
533RR/RDA/08/25/23
Epitakaduwa Krishantha Senarath Yapa Road (Eptakaduwa Budu medura to Mr. LG Jaga…
—
7,231,417.22————————————
534RR/RDA/07/25/14
Moonugoda Road
—
21,211,506.60————————————
535RR/RDA/08/25/05
Koggalla bus stand to Sooriyawewa Road
—
127,573,213.52————————————
536RR/RDA/07/25/22
Asphalting Meepawala henegewaththa road
—
21,395,564.10————————————
537RR/RDA/07/25/21
Asphalting Newungala Na tree to Bedimeda road
—
35,369,824.16————————————
538RR/RDA/07/25/01
Keselgahahena Pradana Margaya (Kanu Paddathiya Bokku Samaga)
—
76,680,545.16————————————
539RR/RDA/08/25/22
Kirinda Roundabout Road with drainages
—
23,083,588.28————————————
540RR/RDA/08/25/02
Andaledduwa Road
—
24,533,049.28————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 531–540 of 579 projects · page 54/58