TRACKING PROGRESS·DELIVERING OUTCOMES

Weekly PhysicalProgress

Track weekly physical progress and manual expenditure for 288 awarded projects — planned vs actual by Friday.

2026-11-04
08:52:04Live2026-11-04

Quick Fill — Physical Progress & Expenditure

218 delayed
Implementation Method
Province
District
Consultant
EE Division
Progress
Show completed Excel
RR/RDA/04/25/13/CP/KY

Gonaala Pasala Asala Sita Kubukkadura Athuru Margayak Wana Gurumada Margaya

Dharshana Construction

2026-10-30

— 🔒

Locked

75 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/19/CP/KY

Mulgama viduhala Asala sita lewalan dakwa

The Wise Lanka Construction Company (Pvt) Ltd

2026-10-30

— 🔒

Locked

294 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/20/CP/KY

Carpeting road Ratemulla to Wendesiwaththa End

Wiscon (Pvt) Ltd

2026-10-30

— 🔒

Locked

272 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/21/CP/KY

Galaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa Margaya

UGD Constructions

2026-10-30

— 🔒

Locked

308 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/24/CP/KY

Galamuduna gamata pivisena Margaya

NAGMA ENGINEERING (PVT) LTD

2026-10-30

— 🔒

Locked

—

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/25/CP/KY

Delgasthenna Road

NAGMA ENGINEERING (PVT) LTD

2026-10-30

— 🔒

Locked

182 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/28/CP/KY

Dehideniya sita Hedeniya dakwa Margaya

Senerath Engineering (pvt) Ltd

2026-10-30

— 🔒

Locked

285 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/31(1)/CP/KY

Paththunupitiya School road to Gampola Road through Pallegama Anguruwala

Central Engineering Services Pvt Ltd. (CESL)

2026-10-30

— 🔒

Locked

120 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/41/CP/KY

Karyala handiya pahala margya concrete kirima

UGD Constructions

2026-10-30

— 🔒

Locked

294 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Ambakote Road

Dharshana Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/52/CP/KY

Bokalawela Road from Hapugoda Junction to Ranawana (Drinage System Development and Road)

Senerath Engineering (pvt) Ltd

2026-10-30

— 🔒

Locked

74 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/04/25/53/CP/KY

Road from Amuvandeniya to Magurudeniya (development of the drainage and carpeting of the road)

Tiasa Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the Dolapihilla road from Navinnapitiya via Deldeniya

Ajith Construction

2026-10-30

— 🔒

Locked

30 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Development of entrance roads, pedestrian rest areas and parking areas of the Sri Dalada Maligawa premises

Southern Group Civil Construction (Pvt) Ltd.

2026-10-30

— 🔒

Locked

89 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Renovation of road Haidri estate to Barcapal

Ajith Construction

2026-10-30

— 🔒

Locked

16 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/07/CP/MTL

Uladawa Mansandiye sita Homapola Janapadaye Saukkaya Maddayasthanaya dakawa Diwena Udurmpelessa thek Diwena Margaya Kapat Kirima

Ajith Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/09/CP/MTL

Ilukkumbura Samurdhi karyalaya asala Patti ela pilama dakwa

Pragathi Civil Contractor

2026-10-30

— 🔒

Locked

285 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/10/CP/MTL

Sonuththa pradana margaye Shailatharamaya idiriye sita 80 yaya dakwa

NAGMA ENGINEERING (PVT) LTD

2026-10-30

— 🔒

Locked

191 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/11/CP/MTL

Hunukete sita Elagala dakwa Pradana Margaya

Senerath Engineering (pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/26/CP/MTL

Pallepola saukya karyalaye sita ekamuthugama dakwa margaya

Jayaru Engineering (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/30/CP/MTL

Ganadewi pilimaya asala Kulathunga mahathage welanda sala dakwa

Lahiru Construction & Consultants (PVT) Ltd

2026-10-30

— 🔒

Locked

86 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/32/CP/NE

Nanuoya Glaso pahala kotasa Margaya

wiscon (pvt) ltd

2026-10-30

— 🔒

Locked

168 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/34/CP/NE

Udupussellawa margaye Amasta handiye sita Ambagasdowa dakwa Margaya

NAGMA ENGINEERING (PVT) LTD

2026-10-30

— 🔒

Locked

182 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/38/CP/NE

Ketahira Gallella margya palama haraha Udagama dakwa Margaya

NAGMA ENGINEERING (PVT) LTD

2026-10-30

— 🔒

Locked

182 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/40/CP/NE

Walapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa Margaya

UGD Constructions

2026-10-30

— 🔒

Locked

299 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/41/CP/NE

Nayapana Gammada tharapara sanwardhanaya

Central Engineering Services Pvt Ltd. (CESL)

2026-10-30

— 🔒

Locked

98 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/42/CP/NE

AC Overlaying from Polpitiya Junction to 04th Mile Post (CH 3+700 – 8+700 km)

UKS Lanka Engineering Pvt Ltd.

2026-10-30

— 🔒

Locked

74 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Carpeting of road from Bambaragama Moragollahinna to Karamidula

Ajith Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Carpeting of Mahathenna to Hapugasdeniya Main Road

Ajith Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/03/AKK/AMP

Polbedda Junction to Galwalayaya Road

MOTEC Engineering & Construction

2026-10-30

— 🔒

Locked

239 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/SP/16/25/01/AKK/AMP

Rectification and Asphalt Surfacing on Ambahagawela -Namaloya Main Road

SMA Careem Engineering Consultancy Services & Suppliers (Pvt) Ltd

2026-10-30

— 🔒

Locked

127 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/STA II/16/25/03/AKK/AMP

Padiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge

Vithu Construction

2026-10-30

— 🔒

Locked

162 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/01/AKK/AMP

The road from the bridge near Ridee ela Temple to Island Plot No. 197

Sawsiri Construction

2026-10-30

— 🔒

Locked

162 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/02/AKK/AMP

Road from Nelum Cafe Junction to Neeththa

Gama Construction & Consultant pvt Ltd

2026-10-30

— 🔒

Locked

152 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/03/AKK/AMP

On the road from Pulungasmulla to Padawala, the road from near Shanta Veladasala towards Padawala

Sawsiri Construction

2026-10-30

— 🔒

Locked

163 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/04/AKK/AMP

Vevinna Boogas Junction Inner Road

Gama Construction & Consultant pvt Ltd

2026-10-30

— 🔒

Locked

180 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/05/AKK/AMP

Road from Dorapaha Junction to Navagiriya Lake

Ema Constructions (Pvt) Ltd

2026-10-30

— 🔒

Locked

150 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/07/AKK/AMP

Bedirakka Malgastalawa Road

Pearl Construction

2026-10-30

— 🔒

Locked

173 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/08/AKK/AKK

RDS Road Addalachena 6, 8

MLH & sons Construction

2026-10-30

— 🔒

Locked

161 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/11/AKK/AKK

Kalyana Road - Periyanilavanai Vishnu Kovil Road to Maradamuna Mashur Maulana Road

Zaka Engineering Consultancy

2026-10-30

— 🔒

Locked

151 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/16/25/10KM/13/AKK/AKK

Jaica - Tsunami Village Road

Gama Construction & Consultant pvt Ltd

2026-10-30

— 🔒

Locked

144 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/02/EP/BTC

Concreting to Samurthi 1st Cross road

Kumaran Construction and Civil Works

2026-10-30

— 🔒

Locked

636 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/15/EP/BTC

Concrete to the Majma Nagar Mullivattuvan at paper town 210B

KMC Construction

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/05/EP/BTC

Concreting to Mailanthanai Sri Muththumariyamman Main Road

Kumaran Construction and Civil Works

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/09/EP/BTC

Concreting to NHDA Housing Scheme Internal Road 1st 2nd Cross

DKJ Construction

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/11/EP/BTC

Concreting to Kali Kovil Road

Jeezan Trading and Transport

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/12/EP/BTC

Concreting to Muthalaikuda to Munnaikkadu Boundary Road

Kumaran Construction and Civil Works

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/13/EP/BTC

Concreting to Sangarpuram- Vilavadi

Kumaran Construction and Civil Works

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/14/EP/BTC

Concreting to Agriculture Road

Jeezan Trading and Transport

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10KM/01/BTC

Sooriya farm Road sathurukondan

Ganan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10KM/02/BTC

Iruthayapuram west 8th cross

Sanju Civil Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10KM/06/BTC

Al Ameen Vidyaya Road

Nathan's Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10KM/07/BTC

Kanady cross Road to Magalingeshwarar kovil Road

Motec Engineering & Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10KM/08/BTC

Poosakar Road, Kannakipuram, Mahiloor

Nathan's Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/05/EP/TRN

Improvement to Jeyanthiwewa to Track 12 Main Road

Nirupama Construction

2026-10-30

— 🔒

Locked

127 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/06/EP/TRN

Malporuwa to Thalgaswewa

Jeezan Trading and Transport

2026-10-30

— 🔒

Locked

127 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/09/EP/TRN

School-Galmetiyawa Main Internal Road

Zaka Engineering Consultancy

2026-10-30

— 🔒

Locked

75 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/11/EP/TRN

Development of Road from near the Fair

MS Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/19/EP/TRN

Periya Suwami Kovil Road-Concrete

Motec Engineering & Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/SP/17/25/03/EP/TRN

Hajra Road (Alhira Jalaira Road)

STAAR Construction

2026-10-30

— 🔒

Locked

75 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/STAII/17/25/03/EP/TRN

From No.908 house to No.904 house road

Soyuru Sampath Construction & Suppliers

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/STAII/17/25/04/EP/TRN

From No.851 house to Rajaela road

ARN Engineering & Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/01/EP/TRN

Road behind th hospital up to the morgue junction

Soyuru Sampath Construction & Suppliers

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/02/EP/TRN

LB cannel bridge to pachchimarama temple

Rina Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/03/EP/TRN

Ethabendiwewa Second Lane

Nathan's Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/04/EP/TRN

Kajuwaththa gama meda road

NMST Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/06/EP/TRN

Budu pilima and 4th lane road

RS Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/07/EP/TRN

Kawanthissa mawatha and in front of the cementerv road

Rina Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/08/EP/TRN

Paththini Amman Kevil road

Alpha Engineering Services & Suppliers

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/10KM/09/EP/TRN

Bazar mosque road

MTA Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/01/NCP/ANP

Road from Thambuttegama - Nochchiyagama road to the road near the DIG's office of Thambuthegama Rajanganaya

Creates Consultant and Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/03/NCP/ANP

Thalawa - Eppawala margaye kele Amunukola handiyen aramba vee kele amunukola viddiyalayen divena margaya

Dissanayaka Builders

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/04/NCP/ANP

A - 9 maragayen aramba vee wale kade dakwa margaya

Dissanayaka Builders

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/06/NCP/ANP

Ududumbara boogas handiye sita sarakkugala pasal handiya dakwa margaya

Dissanayaka Builders

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/11/NCP/ANP

Palayakulama sita halmillakulama dakwa margaya

Dissanayaka Builders

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/16/NCP/ANP

Hiriwadunna handiye sita idigaswewa pansal handiya dakwa margaya

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/18/NCP/ANP

Pahala Talawa road of Thalawa Andarawewa road

HPS Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/20/NCP/ANP

Development of the road from near the Siri Sambodhi Viharaya, 4th Mile post, on the Airport Roundabout Road to the house of Mr. Peme

HPS Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/22/NCP/ANP

Development of the road starting from Mahamankadawala School and extending to Yalegama

D.M.C. CONSTRUCTION (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/26/NCP/ANP

Development of IV lane from Nuwara Road to Mihinthalaya Road

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/28/NCP/ANP

Development of Rathnayake Mawatha

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/25/29/NCP/ANP

Development of the road from Udugama Colony rural road near the A9 road to the front of Mr. Somaratne Senanayake's house

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road starting from Padaviya Kabithigollewa Road to Buddhangala Temple

NMST Contractor

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of road from Sripura main road to 38 Kolaniya Cemetery

NMST Contractor

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of first phase of road from Punewa to Warakwewa

RSW Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from Punewa Junction to Kudahalmillewa Lake

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from near Ikirigollawa Muslim Maha Vidyalaya to Ratmalgahawewa main road from near Ikirigollawa dam to Ratmalgahawa road

WGL Holdings

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

From Makicchawa Junction to Temple (to Kulumiwakada Junction)

Priyantha Civil Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Paddy Depot Road near Padaviya Divisional Secretariat to the entrance road to the archaeological reserve.

Pathiraja Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

road from near Mekichchawa Temple to Gammehegewewa.

Kumari Konthrathkaruwo

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Maradankulam Weerakele Temple Road.

Lisal Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/21/25/03/NCP/POL

Mahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kireema

Nadun Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

238 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/21/25/17/NCP/POL

Development of the road from Kaduruwela Muslim Kolaniya road to Pachcha Palliya

Central Engineering Services Pvt Ltd. (CESL)

2026-10-30

— 🔒

Locked

72 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/21/25/17/NCP/POL

Development of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum Mawatha

Nadun Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from near the Pimburatthewa Mahaweli Resort to the Aralaganwila Maha Oya main road

Sawsiri Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from near the railway on the entrance road to the house of Mrs. 286 Latha in Boatta village

Nathan's Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from the main road to near the Kadawala Wewa School

Nadun Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the road from near the house at Pulastigama 156 to Sungawila 1 Canal Junction

Nadun Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Road from near the Wota Gedi Bridge to Dambalu Stores

Nathan's Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/01/NWP/KRG

Development of Egodagama Talakolawewa road

Sri Ram Constructions

2026-10-30

— 🔒

Locked

182 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/04/NWP/KRG

The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridge

Shanho Enterprises Pvt Ltd.

2026-10-30

— 🔒

Locked

148 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/07/NWP/KRG

Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda

Jayasinghe Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

176 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/09/NWP/KRG

Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground

Senerath Engineering (pvt) Ltd

2026-10-30

— 🔒

Locked

246 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/11/NWP/KRG

Development of road from Dambulu Road to Havanathenna via Ehelagollaya

Shanho Enterprises Pvt Ltd.

2026-10-30

— 🔒

Locked

126 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/22/NWP/KRG

Paving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.

Jayasinghe Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

153 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/135/NWP/KRG

Kelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat Kirima

Jayasinghe Contractors (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/137/NWP/KRG

Damunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat Kirima

W P J Engineering(Pvt)Ltd

2026-10-30

— 🔒

Locked

212 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/138/NWP/KRG

Pudukkulama Bogas Handiye sita Keppitiya haraha Thihawa Dakwa Margaya Kapat Kirima

W P J Engineering(Pvt)Ltd

2026-10-30

— 🔒

Locked

211 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/139/NWP/KRG

Akkara Panaha Mansandiye Sita Walahamulla Dakwa Margaya

Jayawansa Construction (PVT) Ltd

2026-10-30

— 🔒

Locked

170 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Wijekoon Mawatha near Narammala Bus Stand and Hospital Mawatha from Peralaswella

Thushara roofing (pvt) ltd

2026-10-30

— 🔒

Locked

94 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/01/NWP/PUT

Development of carpeting the Gammedda road up to Anathapara.

Chandana Construction

2026-10-30

— 🔒

Locked

319 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/04/NWP/PUT

Carpeting of green light carpeted road from Bogus Junction (80 acres).

Sri Ram Constructions

2026-10-30

— 🔒

Locked

240 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/05/NWP/PUT

Development of the road from near Mr. Chaminda's house to Boga Pathaha

Sampath Contractors

2026-10-30

— 🔒

Locked

245 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/08/NWP/PUT

Carpeting of Velasia Main Road from Madurankuliya.

Sri Ram Constructions

2026-10-30

— 🔒

Locked

214 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/27/NWP/PUT

The entrance to the Medical Officer's Office in the Galahitiyawa Grama Niladhari Division

Omega Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

274 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/30/NWP/PUT

Development of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main road

Omega Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

206 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/31/NWP/PUT

Development of carpeting from the point where carpeting has stopped on the Tammana main road

Sampath Construction

2026-10-30

— 🔒

Locked

175 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/32/NWP/PUT

Development of the Bammeyaya Road

Jayawardana Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

176 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/33/NWP/PUT

Development of the road from near the Sugatarama Temple, Periyakulam to Thalgaswewa

Jayawardana Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

206 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/34/NWP/PUT

Carpeting & Development of Bodhirajapura 4th Lane

Sampath Construction

2026-10-30

— 🔒

Locked

176 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/37/NWP/PUT

Lawyer Wijayananda's House Road

Ponnamperuma Suppliers

2026-10-30

— 🔒

Locked

204 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/38/NWP/PUT

North Dummaladeniya Cross Road

Ponnamperuma Suppliers

2026-10-30

— 🔒

Locked

204 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/39/NWP/PUT

Renovation of Khemananda Road

SriLak Import and Export Company

2026-10-30

— 🔒

Locked

199 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Development of the road from Madurankuliya to Velasiya College

Sampath Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of Fenando Road - Picchawala Road

Dilini Builders (PVT) LTD

2026-10-30

— 🔒

Locked

79 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/01/NP/JFN

Maveli Periyathurai Road. 3.6509

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/06/NP/JFN

Renovation of West beach Road

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

200 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/14/NP/JFN

Pankuru Veethy

Thaaru Construction

2026-10-30

— 🔒

Locked

162 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/18/NP/JFN

Atchuvely Industrial Road

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

214 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/22/NP/JFN

Anaivilunthan Sudalai Road

Yaso Engineering

2026-10-30

— 🔒

Locked

215 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/25/NP/JFN

Palaiya Vaikal Veeethy

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

216 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/01/NP/VVN

Thiruchchenthooran mill road NVSTE541

TMC Constructions

2026-10-30

— 🔒

Locked

36 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/03/NP/VVN

Puthiya manipuram, main road (NVSTE481)

Yaso Engineering

2026-10-30

— 🔒

Locked

264 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/04/NP/VVN

Suntharapuram main road

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

154 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/17/NP/VVN

Lyca village enterance Road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/22/NP/VVN

Mannankerny road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/52/NP/VVN

Menanager Malakattu Kalkuwari Road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/07/NP/VVN

Tharanikulam main road

Sintha Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

255 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/10/NP/VVN

Achchipuram amman temble road

Ancheneya Constructions

2026-10-30

— 🔒

Locked

271 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/12/NP/VVN

Nanthimiththiragama 1st

Ancheneya Constructions

2026-10-30

— 🔒

Locked

166 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/13/NP/VVN

Nanthimiththiragama 2nd

Ancheneya Constructions

2026-10-30

— 🔒

Locked

196 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/14/NP/VVN

Nanthimiththiragama 4th

Ancheneya Constructions

2026-10-30

— 🔒

Locked

196 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/18/NP/VVN

Nedunkerny North sandankulam Road

Yaso Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/19/NP/VVN

Senaipilavu Road

Yaso Engineering

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/20/NP/VVN

Puthiyakudiyiruppu parasankulam road

Bapithan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/21/NP/VVN

Bagaswewa 01st 22nd lane

Bapithan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/24/NP/VVN

Kanagarayankulam puthuvilankulam road (NVVNE073)

Bapithan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/25/NP/VVN

2nd cross Lane Ginigathhena

Nimna Holdings (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/27/NP/VVN

From Acre 400 7th Lane to cross end of the 2nd internal road close to Andarawewa

Ranasinghe Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/28/NP/VVN

From Janaudanagama 2nd internal road to end of the free school

North Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/29/NP/VVN

Kalasiyambalawa Road

North Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/31/NP/VVN

Mahakachchakodiya to Ettambagaskada

Yansika Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/35/NP/VVN

Awusadapitiya Pubudugama Road

Nimna Holdings (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/38/NP/VVN

Salalinigama 11 lane

Sintha Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/40/NP/VVN

Halabagaswewa

North Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/41/NP/VVN

Arasadikulam - veerapuram road (2km) veerapuram 1st lane (NVVPE227)

Omega Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/43/NP/VVN

Pavatkulam tack 5 vaarikuttiyoor

North Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

255 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/48/NP/VVN

Mukaththankulam 7th lane (NVVPE173)

Sintha Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

255 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/51/NP/VVN

Adappankulam aladi road

North Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

255 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/54/NP/VVN

Nikawewa Right Village Road

Yansika Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/60/NP/VVN

Salalinigama lane 12

Sintha Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

124 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/62/NP/VVN

Periyavilathikulam

Omega Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

124 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/63/NP/VVN

1st Cross Street Alakarai Road

North Construction

2026-10-30

— 🔒

Locked

167 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/12/25/64/NP/VVN

Nedunkulama

Arul Selvi Construction and Hardware

2026-10-30

— 🔒

Locked

124 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/01/NP/MUL

Akkaraiveli Paraiyanaru ( Vilaththiyad) Road Package 1

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

247 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/03/NP/MUL

Navatkadu Road

TMC Constructions

2026-10-30

— 🔒

Locked

217 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/06/NP/MUL

Pandaravanniyan Silaiyadi Road

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

223 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/07/NP/MUL

Kanagarayankulam District Boundary Road (Old Kandy road)

Sun Constructions (Pvt) Ltd.

2026-10-30

— 🔒

Locked

223 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/08/NP/MUL

Kumulamunai Akkarayan road

Nimna Holdings (Pvt) Ltd

2026-10-30

— 🔒

Locked

217 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/10/NP/MUL

Pandiyankulam Neddankandal Road

Nimna Holdings (Pvt) Ltd

2026-10-30

— 🔒

Locked

217 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/13/25/11/NP/MUL

Ethawetuvuwewa to Sampathnuwara

Nimna Holdings (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RDA/GOSL/NP/RR/LCB/PACKAGE 2(MU)

Thapaalaga veethi Section I &II, 2nd Cross Road, Kallappadu kadtkarai Main Road, Koolamurippu kerudamadu enaippu veethi and Olumadu Pullmachchinathikulam Ampakamam Road

RR Construction (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/01/NP/MNR

Mahilankulam Pallamadhu road

George Steuart Engineering (Pvt)Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/02/NP/MNR

Piramanayankulam Parappukadanthan road

George Steuart Engineering (Pvt)Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/03/NP/MNR

Kaddadivayal Ramayankulam Naddankandal road

Nimna Holdings (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/04/NP/MNR

Tharavankottai to Keeri Main Road

VN Construction JV

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/07/NP/MNR

Avithappar Panimayam Internal Road with Culvert - Pesalai

VN Construction JV

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/11/NP/MNR

Eruvittan - Vellalakaddu Road

VN Construction JV

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/05/NP/MNR

Konnayan Kudiyiruppu Internal Main Road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/06/NP/MNR

Martin Road

Pastini Construction Material Supply

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/09/NP/MNR

Renovation of Mathirikiramam internal Road Naruvilikulam

Abdul Cader Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/16/NP/MNR

P.P.Potkerny Scheme Internal Road 1

Abdul Cader Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/18/NP/MNR

Akaththimurippu Internal Road 3

Abdul Cader Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/20/NP/MNR

Kondachchi to Pasithenral Road

Abdul Cader Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/22/NP/MNR

School back side road

Sintha Construction (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/11/25/23/NP/MNR

Palakaimunai Beach Road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Pallavarayankaddu Junction - Kiranchi - Ponnaveli Road

Nimna Holdings (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/14/25/06/NP/KLN

Skanthapuram Kannan Temple road

Sun Constructions (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/14/25/07/NP/KLN

Mayilvakanapuram kolunthupulavu road

RR Construction (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/14/25/08/NP/KLN

Kalmadu 7th unit 3rd lane

Kanola Constructions & Engineering (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/14/25/09/NP/KLN

Neliyai Amman kovil road

Kanola Constructions & Engineering (Pvt) Ltd

2026-10-30

— 🔒

Locked

239 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/10/25/24/NP/KLN

Kevil Nithtiyaveddai Road 2.150

Kanola Constructions & Engineering (Pvt) Ltd

2026-10-30

— 🔒

Locked

239 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RDA/GOSL/NP/RR/LCB/PACKAGE 1(KN)

Vannerikulam Jeyapuram Road, Anaikkaddy Road, Veddukkaddu Road Sec.i & iii and Sekkalai Mudkompan Road

RR Construction (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/01/SBP/RTP

From Delgas Junction To Vilehena Road

Siri Construction

2026-10-30

— 🔒

Locked

324 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/02/SBP/RTP

Thundola Varathenna Road

Siri Construction

2026-10-30

— 🔒

Locked

186 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/03/SBP/RTP

From Thunaghahena To Temple Road

Siri Construction

2026-10-30

— 🔒

Locked

324 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/10/SBP/RTP

From Deniya kade Market to Henyaya Road Via Keenagahaella Road

Sam Dam

2026-10-30

— 🔒

Locked

191 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/21/SBP/RTP

Sudagala Grama Seva Division, From Sudagala to Tunudola Road up the mountain to near the cooperative

DKS Construction

2026-10-30

— 🔒

Locked

22 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/25/SBP/RTP

From the point where the Bulathgama-Pallevela road starts from Rasagala Road

Sathira Construction

2026-10-30

— 🔒

Locked

18 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/28/SBP/RTP

From near Kalal Ella Rubber Store to Narangalla via Navinikanda Road

KEP Construction

2026-10-30

— 🔒

Locked

5 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/31/SBP/RTP

Development of Koratuwegoda Road from Main Road

KEP Construction

2026-10-30

— 🔒

Locked

29 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/32/SBP/RTP

Weligepola to Nitta Kumbura Road

Sasiri Construction

2026-10-30

— 🔒

Locked

18 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/34/SBP/RTP

Matuwagala Mudun Kotu Road

DKS Construction

2026-10-30

— 🔒

Locked

22 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/24/25/35/SBP/RTP

Induruwa Junction to Kadawatha junction road joining Kuruwita - Siripagama road

Creates Consultant and Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/02/SBP/KGL

Elagapitiya Colany Road From Debathgama Pallebage to Tea Shakthi Praja Shalawa

EHL Constructions

2026-10-30

— 🔒

Locked

184 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/03/SBP/KGL

From Kehelpannala Junction to Pahala Kabawita Road

SF Constructions

2026-10-30

— 🔒

Locked

188 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/09/02/SBP/KGL

The first phase of the Gaitahpura road via Ambagala on the Warakapola Technical College Road

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/15/SBP/KGL

Moraliya Gagaboda Road

DHP Construction

2026-10-30

— 🔒

Locked

276 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/20/SBP/KGL

Neluwakkana gama meda Road

Loshitha Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/28/SBP/KGL

Naagas thenna Road

Jayasinghe Contractors (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/34/SBP/KGL

Road Connecting Ihala Palampitiya and Pahala Palampitiya

DKS Nishantha Construction

2026-10-30

— 🔒

Locked

13 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/35/SBP/KGL

Kudadeniya Adurapola Watta Road

TMT Construction

2026-10-30

— 🔒

Locked

155 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/38/SBP/KGL

Development of the road near the closed tea factory on Edurapola Watta main road

TMT Construction

2026-10-30

— 🔒

Locked

153 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/39/SBP/KGL

Development of Gatayamulla Jagatpura Pannala Rasnadeniya road

Samindra Construction

2026-10-30

— 🔒

Locked

65 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/25/40/SBP/KGL

Kabagamuwa 17 Acres Road Development

TMT Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/02/SP/GAL

Delgahabedda-Kirimatiya Margaya

Dissanayaka Builders

2026-10-30

— 🔒

Locked

323 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/05/SP/GAL

Atawalawatta Sri Rewatha Viduhala Idiripita Margaya

Dissanayaka Builders

2026-10-30

— 🔒

Locked

323 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/09/SP/GAL

Panwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa Margaya

DGSD Construction

2026-10-30

— 🔒

Locked

323 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/13/SP/GAL

Aganaketiya Anuruddagama Mansandiye sita Samagipura dakwa Pradana Maragaya

EHL Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/17/SP/GAL

Dasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirima

P.H. Engineering Construction (Pvt) Ltd

2026-10-30

— 🔒

Locked

323 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/19/SP/GAL

SuriEla Margaya

A.D. Herath Engineering

2026-10-30

— 🔒

Locked

300 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/05

Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culverts

EHL Constructions

2026-10-30

— 🔒

Locked

44 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/08

Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards Dolahena

Kumarage Enterprises(Pvt)Ltd

2026-10-30

— 🔒

Locked

42 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/12

9 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta Road

Kumarage Enterprises(Pvt)Ltd

2026-10-30

— 🔒

Locked

42 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/14

Kodagoda Thudugala Road

Jayathissa Construction

2026-10-30

— 🔒

Locked

44 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/18

Expansion of Alikehena Road from Thalawa Junior College to Atakohota border

S.A.Construction

2026-10-30

— 🔒

Locked

50 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/20

Development of Paramount City Road.

EHL Constructions

2026-10-30

— 🔒

Locked

47 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/21

Concretisation of Dikhena Welamedda road up to Addunkelle with 2 culverts and side walls on both sides.

Isula Construction

2026-10-30

— 🔒

Locked

47 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/26/10KM/22

Kapalwila Olympus Waththa I.K. Road from Mr. Sunil's house to Rakshana Village Bodhi near Ketagoda Kada.

Woshitha Engineering(Pvt)Ltd

2026-10-30

— 🔒

Locked

44 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/08/25/18/SP/MTR

Dekatukella Margaya Pethibemma sahithawa Sanwardanaya kirima

Dashodhaya (Pvt)Ltd

2026-10-30

— 🔒

Locked

300 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Development of the road by laying Asphalt starting from near Saddhatissa Junior College on the Panattiyana-Weligama road up to Barawadeniya Junction

GEL Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of the Pathegama Temple Road (Massalatiya Road) by carpeting

GEL Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/08/SP/HMB

Carpeting Pissubedda Medagamgoda road

Samarasinghe Construction(Pvt)Ltd

2026-10-30

— 🔒

Locked

138 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/09/SP/HMB

Development of the road in front of Godawela School to Ambussa Wela

A.T.L. Construction

2026-10-30

— 🔒

Locked

104 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/11/SP/HMB

Development of Walasmulla Daluwakgoda School Road

Samarasinghe Construction(Pvt)Ltd

2026-10-30

— 🔒

Locked

62 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/13/SP/HMB

Development of the road from Puak Dandawa near Aligerappa house through Weerasijahagoda to Satinamaluwa Kapuduarawatta field.

A.T.L. Construction

2026-10-30

— 🔒

Locked

105 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/26/01

From near the Bedigama North Health Center to Indimandiya

Isula Construction

2026-10-30

— 🔒

Locked

50 days left

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/22/25/07/UP/BDL

Tharuna Govipola Margaye ithiri Kotasa Sanwardanaya Kirieema

Samadhi Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/22/25/09/UP/BDL

Piyarapandowa Neluwa Margaya

Liyanage Contractors

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/22/25/22/UP/BDL

Achchupatti Margaya

Priyankara Industries and Contractors

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/25/14/WP/COL

Development of the section from Arangala Bridge to Mihindu Mawatha in Malabe West Division

W.A. Perera & Company (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/25/19WP/COL

Puwakpitiya Dharmalapala Mawatha Main Road Development of the road from High Level Road to Elstonwatte Volleyball Court

Asela Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/25/26/WP/COL

Boraluwathenna Pahala Uda Road

Next Engineering Services (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/25/30/WP/COL

Development of the road from near the transformer near Seebara Kade, Boralugoda to the Jayanthi Road

Asset Engineering (Pvt)LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/02/25/03/WP/GMP

Development of De silva road beginning from Angurukaramulla temble road to Negombo Colombo road

Dilini Builders (PVT) LTD

2026-10-30

— 🔒

Locked

37 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/02/25/08

Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.

Wijerathna Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

The road from Thaladuwa Road near Negombo Bus Stand, passing Jude Church, to the cemetery

Dilini Builders (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Road from Pinnawatta Junction to Mr. Sandaruwan's shop on the Hapitiya entrance road

Jeyanthan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Udupila South Dolewatta

Creates Consultant and Construction

2026-10-30

— 🔒

Locked

113 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/02/25/18/WP/GAM

Peliyagoda Naranminiya Road

Ceylux Civil engineering (Pvt) Ltd

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

3 A road carpeted development near the Japanese Montessori at the junction of the North Kadirana Division.

Jeyanthan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

241 B Near Weliweriya North Suruwama Junction to Weliweriya Town

Yagoda Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Near Urapana Sisira Coir Mill to Hapugahagama Co-operative

Jeyanthan Construction

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/03/25/12/WP/KTR

Concreting Batawala Road

Next Engineering Services (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of 2.64 km section of Neluwa-Karapagala road with carpet

EHL Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/03/25/WP/KLT/15

Development of 1.5 km carpeting of Suduvelipatha Athale road from near Suduvelipatha bodhia towards Athale school

EHL Constructions

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/03/25/16/WP/KTR

Development of carpeting of 1 km from Gane Aramba Road, Bogalla Junction to Ambepitiya Pinhena

Asela Construction

2026-10-30

— 🔒

Locked

124 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Development of 0.8 km carpeting of Newfa Mawatha

Develco Engineering (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/03/25/18/WP/KTR

Development of carpeting of the section (length 800 m) from near Minerithenna temple to Jananandanarama temple

Asela Construction

2026-10-30

— 🔒

Locked

124 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

Carpeting and development of 500 meters of Moragahakanda watta Bodumaga Senasuna Viharastha Road

Develco Engineering (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

Development of from Lewis Stadium to Heladiva Malshalawa

Develco Engineering (PVT) LTD

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RDA/GOSL/WP/RR/LCB/Pacakge2(KL)

From Addaragoda Weepella Road via Wedigoda, Gulanwatta Nawala Mandagala Road and Boralugoda Thiniyawala Road

RR Construction (Pvt) Ltd.

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/44

Carpeting of Muloya Main Road Section 2

—

2026-10-30

— 🔒

Locked

308 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/06/25/47

Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala

—

2026-10-30

— 🔒

Locked

308 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/23

Manchanayake shed eka asala sita sampath waththa haraha Galketiyawa margaya

—

2026-10-30

— 🔒

Locked

144 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/05/25/28

Adawala Udagama Road

—

2026-10-30

— 🔒

Locked

255 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/15/25/10

Concreting to Internal at MMV School

—

2026-10-30

— 🔒

Locked

354 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/17/25/08

Concreting of Play Ground Road Mahadiulwewa Stage II

—

2026-10-30

— 🔒

Locked

218 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/20/26/23

First phase of Priman Mawatha via the by-road behind Kumbichchankulama tank

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/21/25/17

Hingurakgoda Samupakara Road to Bubula

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/18/25/309

From near Kongaha in Waudagama on the Katupotha Waudagama Wanduressegama road near Potuwewa Cemetery.

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/19/25/36

Renovation of Warusavithana Laboratory Road

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/35

Ilumba Kanda Road from Milinduthalawa Temple

—

2026-10-30

— 🔒

Locked

218 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/17

Pahalawaththa to Batahenkanda Road

—

2026-10-30

— 🔒

Locked

218 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/19

Wijeriya Iththekanda Margaya Sanwardanaya Kirima

—

2026-10-30

— 🔒

Locked

218 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/25/24/20

Godawela Walakada margaya Sanwardanaya Kirima (Walakada Junction to Godawela Junction)

—

2026-10-30

— 🔒

Locked

218 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/08/25/05

Koggalla bus stand to Sooriyawewa Road

—

2026-10-30

— 🔒

Locked

323 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/07/25/01

Keselgahahena Pradana Margaya (Kanu Paddathiya Bokku Samaga)

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/12

Development of the road from Lunugamwehera Jadura Lake to Udaeva

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/06

Raluwa main road

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/07

Carpeting Dabewelena Gravel Road

—

2026-10-30

— 🔒

Locked

308 Days in Delay

Expenditure · LKR Mn incl. VAT

2026-10-30

2026-11-06

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/14

Development of road near Olu ara School

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/09/25/10

Development of Valasmulla Pallekanda road from 3 km post to 5 km post

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/25/21

Development of Yakala Cemetery Road up to Welihinda Bridge by carpeting

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/26/10KM/01

Development of Honnatthara South Kudamadhuwa Road, Moonamalgahawatte Road up to House No. 138/3 by laying carpet and installing drains.

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/26/01

Major Alagiyawanna Road to Welivita Road

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.

RR/RDA/01/26/05

Malabe Chandrika Kumarathunga Road

—

—

—

2026-11-04

Expenditure · LKR Mn incl. VAT

—

—

2026-11-04

Blank current week = paid IPC total incl. VAT.