DRRRP Awarded Tender Tender Below 50Mn

Development of first phase of road from Punewa to Warakwewa

AnuradhapuraNorth Central ProvinceMedawachchiyaDivisional SecretariatRSW EngineeringContractorLKR 29,762,232.50Contract Sum0 daysProject Duration
25%
Complete
Physical Progress25%
Planned Progress0%
Time Elapsed0%
14 days behind schedule

Project Timeline

LOA
2026-07-15
Completed
Possession
–
Pending
Commencement
2026-07-29
Completed
Scheduled Completion
2026-10-21
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Central Province
DistrictAnuradhapura
DS Division-
GN Division-
Electorate-
PD RegionNorth Central Province
CE RegionAnuradhapura
EE DivisionMedawachchiya
Authority Tier-
Authority Name-
Package No.RR/RDA/20/25/55
Tender ByProvincial Director