DRRRP Awarded Tender Tender Below 50Mn

Development of road from Sripura main road to 38 Kolaniya Cemetery

AnuradhapuraNorth Central ProvinceMedawachchiyaDivisional SecretariatNMST ContractorContractorLKR 27,971,333.13Contract Sum0 daysProject Duration
2%
Complete
Physical Progress2%
Planned Progress0%
Time Elapsed0%
13 days behind schedule

Project Timeline

LOA
2026-07-16
Completed
Possession
–
Pending
Commencement
2026-07-30
Completed
Scheduled Completion
2026-10-22
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Central Province
DistrictAnuradhapura
DS Division-
GN Division-
Electorate-
PD RegionNorth Central Province
CE RegionAnuradhapura
EE DivisionMedawachchiya
Authority Tier-
Authority Name-
Package No.RR/RDA/20/25/53
Tender ByProvincial Director