DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/18/25/01/NWP/KRG

Development of Egodagama Talakolawewa road

KurunegalaNorth Western ProvinceMahoDivisional SecretariatSri Ram ConstructionsContractorLKR 98,323,766.14Contract Sum119 daysProject Duration
60%
Complete
Physical Progress60%
Planned Progress100%
Time Elapsed100%
182 days behind schedule

Project Timeline

LOA
2025-11-25
Completed
Possession
–
Pending
Commencement
2026-01-08
Completed
Scheduled Completion
2026-05-06
Completed
Anticipated Completion Date
2026-07-09
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionMaho
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/01
Tender ByProcurement Division