DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/04/25/28/CP/KY

Dehideniya sita Hedeniya dakwa Margaya

KandyCentral ProvinceKandyDivisional SecretariatSenerath Engineering (pvt) LtdContractorLKR 38,495,776.00Contract Sum119 daysProject Duration
35%
Complete
Physical Progress35%
Planned Progress100%
Time Elapsed100%
285 days behind schedule

Project Timeline

LOA
2025-09-26
Completed
Possession
–
Pending
Commencement
2025-10-25
Completed
Scheduled Completion
2026-01-23
Completed
Anticipated Completion Date
2026-04-10
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
DS Division-
GN Division-
Electorate-
PD RegionCentral Province
CE RegionKandy
EE DivisionKandy
Authority Tier-
Authority Name-
Package No.RR/RDA/04/25/28
Tender ByProvincial Director