DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/25/24/01/SBP/RTP

From Delgas Junction To Vilehena Road

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatSiri ConstructionContractorLKR 30,346,327.41Contract Sum90 daysProject Duration
90%
Complete
Physical Progress90%
Planned Progress100%
Time Elapsed100%
324 days behind schedule

Project Timeline

LOA
2025-09-12
Completed
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-15
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Authority Tier-
Authority Name-
Package No.RR/RDA/25/24/01