DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/17/25/10KM/06/EP/TRN

Budu pilima and 4th lane road

TrincomaleeEastern ProvinceTrincomaleeDivisional SecretariatRS ConstructionContractorLKR 17,520,285.64Contract Sum0 daysProject Duration
15%
Complete
Physical Progress15%
Planned Progress0%
Time Elapsed0%
6 days behind schedule

Project Timeline

LOA
2026-07-16
Completed
Possession
–
Pending
Commencement
2026-07-31
Completed
Scheduled Completion
2026-10-29
Completed
Anticipated Completion Date
–
Delayed