DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/03/25/18/WP/KTR

Development of carpeting of the section (length 800 m) from near Minerithenna temple to Jananandanarama temple

KalutaraWestern ProvinceKalutaraDivisional SecretariatAsela ConstructionContractorLKR 17,101,775.00Contract Sum91 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress100%
Time Elapsed100%
124 days behind schedule

Project Timeline

LOA
2026-03-20
Completed
Possession
–
Pending
Commencement
2026-04-03
Completed
Scheduled Completion
2026-07-03
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictKalutara
DS Division-
GN Division-
Electorate-
PD RegionWestern Province
CE RegionKalutara
EE DivisionKalutara
Authority Tier-
Authority Name-
Package No.RR/RDA/03/25/18
Tender ByProvincial Director