DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/25/25/39/SBP/KGL

Development of Gatayamulla Jagatpura Pannala Rasnadeniya road

KegalleSabaragamuwa ProvinceRuwanwellaDivisional SecretariatSamindra ConstructionContractorLKR 31,491,651.40Contract Sum90 daysProject Duration
95%
Complete
Physical Progress95%
Planned Progress100%
Time Elapsed100%
65 days behind schedule

Project Timeline

LOA
2026-05-19
Completed
Possession
–
Pending
Commencement
2026-06-02
Completed
Scheduled Completion
2026-08-31
Completed
Anticipated Completion Date
2026-08-31
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionRuwanwella
Authority Tier-
Authority Name-
Package No.RR/RDA/25/25/39
Tender ByProvincial Director