DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/17/25/09/EP/TRN

School-Galmetiyawa Main Internal Road

TrincomaleeEastern ProvinceTrincomaleeDivisional SecretariatZaka Engineering ConsultancyContractorLKR 53,122,107.50Contract Sum91 daysProject Duration
50%
Complete
Physical Progress50%
Planned Progress100%
Time Elapsed100%
75 days behind schedule

Project Timeline

LOA
2026-05-08
Completed
Possession
–
Pending
Commencement
2026-05-22
Completed
Scheduled Completion
2026-08-21
Completed
Anticipated Completion Date
2026-07-31
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceEastern Province
DistrictTrincomalee
DS Division-
GN Division-
Electorate-
PD RegionEastern Province
CE RegionTrincomalee
EE DivisionTrincomalee
Authority Tier-
Authority Name-
Package No.RR/RDA/17/25/09
Tender ByProcurement Division