DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/19/25/30/NWP/PUT

Development of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main road

PuttalamNorth Western ProvincePuttalamDivisional SecretariatOmega Construction (Pvt) LtdContractorLKR 38,494,009.50Contract Sum91 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress100%
Time Elapsed100%
206 days behind schedule

Project Timeline

LOA
2025-12-29
Completed
Possession
–
Pending
Commencement
2026-01-12
Completed
Scheduled Completion
2026-04-12
Completed
Anticipated Completion Date
2026-06-12
Delayed