DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/19/25/38/NWP/PUT

North Dummaladeniya Cross Road

PuttalamNorth Western ProvinceChilawDivisional SecretariatPonnamperuma SuppliersContractorLKR 10,005,001.78Contract Sum91 daysProject Duration
90%
Complete
Physical Progress90%
Planned Progress100%
Time Elapsed100%
204 days behind schedule

Project Timeline

LOA
2025-12-31
Completed
Possession
–
Pending
Commencement
2026-01-14
Completed
Scheduled Completion
2026-04-14
Completed
Anticipated Completion Date
2026-04-14
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictPuttalam
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionChilaw
EE DivisionChilaw
Authority Tier-
Authority Name-
Package No.RR/RDA/19/25/38
Tender ByProvincial Director