DRRRP Awarded Tender Tender Below 50Mn
Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
AnuradhapuraNorth Central ProvinceMedawachchiyaDivisional SecretariatPriyantha Civil EngineeringContractorLKR 33,242,915.64Contract Sum0 daysProject Duration
Schedule Delay2 daysbehind schedule
2 days behind schedule
Commencement
2026-08-10
Completed
Scheduled Completion
2026-11-02
Completed
Anticipated Completion Date
–
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceNorth Central Province
DistrictAnuradhapura
DS Division-
GN Division-
Electorate-
PD RegionNorth Central Province
CE RegionAnuradhapura
EE DivisionMedawachchiya
Authority Tier-
Authority Name-
Package No.RR/RDA/20/25/54
Tender ByProvincial Director
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryTender
Implementation MethodTender Below 50Mn
Contract NameDevelopment of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
Estimated Road Lengths1.00 km
Number of Roads1
Scope Summary-
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.-
Tender Batch No.-
Contractor NamePriyantha Civil Engineering
Consultant-
Tender StatusAwarded
LOA Date2026-07-27
Contract Amount33,242,915.64
Engineer Estimate Amount (LKR)40,137,233.68
Duration (Days)-
Tender Process Details Tender
Bid Notice Date2026-04-08
Tender Opening Date2026-04-30
BEC Evaluation Submitted—
PC Decision Date—
Intention to Award—
Appeal Final Date—
Possession of Site—
Completed Date—
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-11-02
Anticipated Completion Date
—
Duration Elapsed86 / 0 days
Schedule Status2 Days in Delay
Anticipated Completion Date—
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress5% vs 0%
Financial Progress0% vs 0%
Progress MonitorOn Progress
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Current expenditure
as at 2026-11-04 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-11-02
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 2 Days in Delay
Overall Progress
Overall
Planned: 0%Ahead by 5%
Financial Actual: 0.00 Mn / Planned 0.00 MnAhead 0.00 Mn
Critical Issues-
Anuradhapura - Medawachchiya
Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
Project Name:
Project #169 - Contract No. -
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 08:57
Contract No. -
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 5%
Set Commenced Date & Duration to generate the physical planned curve.
Go to Mobilization & Contract Period to set dates.
No physical schedule yet - set Commenced Date & Duration to generate.
Presentage
Actual financial
Anuradhapura - Medawachchiya
Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
Project Name:
Project #169 - Contract No. -
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 08:57
Contract No. -
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Set Commenced Date & Duration to generate the financial planned curve.
No financial schedule yet - set Commenced Date & Duration to generate.
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-24
Snapshot value5%
Current progress5%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.