DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/07/25/02/SP/GAL

Delgahabedda-Kirimatiya Margaya

GalleSouthern ProvinceGalleDivisional SecretariatDissanayaka BuildersContractorLKR 26,404,581.16Contract Sum91 daysProject Duration
93%
Complete
Physical Progress93%
Planned Progress100%
Time Elapsed100%
323 days behind schedule

Project Timeline

LOA
2025-09-12
Completed
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2025-12-31
Delayed