DRRRP Awarded Dl DL Stage 03

RR/RDA/06/25/44

Carpeting of Muloya Main Road Section 2

Nuwara EliyaCentral ProvinceHangurankethaDivisional Secretariat-ContractorLKR 42,312,390.95Contract Sum101 daysProject Duration
60%
Complete
Physical Progress60%
Planned Progress100%
Time Elapsed100%
308 days behind schedule

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-22
Completed
Scheduled Completion
2025-12-31
Completed
Anticipated Completion Date
2026-03-15
Delayed