DRRRP Awarded Dl DL Stage 04

RR/RDA/01/25/21

Development of Yakala Cemetery Road up to Welihinda Bridge by carpeting

ColomboWestern ProvinceColomboDivisional Secretariat-ContractorLKR 9,242,749.23Contract Sum0 daysProject Duration
5%
Complete
Physical Progress5%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-03-07
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
2026-03-30
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
DS Division-
GN Division-
Electorate-
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kaduwela