DRRRP Awarded Dl DL Stage 02

RR/RDA/15/25/10

Concreting to Internal at MMV School

BatticaloaEastern ProvinceBatticaloaDivisional Secretariat-ContractorLKR 33,890,314.66Contract Sum99 daysProject Duration
95%
Complete
Physical Progress95%
Planned Progress100%
Time Elapsed100%
354 days behind schedule

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-08-09
Completed
Scheduled Completion
2025-11-15
Completed
Anticipated Completion Date
2026-03-15
Delayed