DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/18/25/137/NWP/KRG

Damunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat Kirima

KurunegalaNorth Western ProvinceKurunegalaDivisional SecretariatW P J Engineering(Pvt)LtdContractorLKR 18,425,029.46Contract Sum91 daysProject Duration
45%
Complete
Physical Progress45%
Planned Progress100%
Time Elapsed100%
212 days behind schedule

Project Timeline

LOA
2025-12-23
Completed
Possession
–
Pending
Commencement
2026-01-07
Completed
Scheduled Completion
2026-04-06
Completed
Anticipated Completion Date
2026-06-06
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionKurunegala
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/137
Tender ByProvincial Director