DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/25/25/35/SBP/KGL

Kudadeniya Adurapola Watta Road

KegalleSabaragamuwa ProvinceRuwanwellaDivisional SecretariatTMT ConstructionContractorLKR 29,362,927.93Contract Sum90 daysProject Duration
60%
Complete
Physical Progress60%
Planned Progress100%
Time Elapsed100%
155 days behind schedule

Project Timeline

LOA
2026-02-18
Completed
Possession
–
Pending
Commencement
2026-03-04
Completed
Scheduled Completion
2026-06-02
Completed
Anticipated Completion Date
–
Delayed