DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-05
04:22:49Live2026-11-05
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
0 / 5Advance Paidadvance paid projects / total projects
0 / 5IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Gampaha · EE: Gampaha · EE Office

15Projects279.0Contract Mn
Gampaha 5 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn338.0—38.0——————33.3%0.0%
DL Stage 01110.54.845% of contract5.8——————100.0%0.0%
DL Stage 03112.19.478% of contract2.6——————0.0%0.0%
DL Stage 0400.0——————————
Gampaha560.614.223% of contract46.4000.0000.040.0%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn3 projects38.0Mn
0% paid0.0 Mn
Pending38.0Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project10.5Mn
45% paid4.8 Mn
Pending5.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project12.1Mn
78% paid9.4 Mn
Pending2.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Gampaha5 projects60.6Mn
23% paid14.2 Mn
Pending46.4Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Gampaha · EE: Gampaha

Project-wise Financials · Gampaha · EE: Gampaha (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Gampaha · EE: Gampaha (Mn · incl. VAT)

Scroll horizontally — 579 projects

Gampaha Division · Gampaha · EE: Gampaha (Mn · incl. VAT)

Gampaha District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:5 awarded · Gampaha · EE: Gampaha
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

491–500/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
491RR/RDA/10/25/17
College Road
—
35,288,918.91————————————
492RR/RDA/12/25/44
Menicfarm school road (0.5km) (NVVPE97)
—
11,100,861.98————————————
493RR/RDA/13/25/09
Aninchiyankulam 2nd Lane MUTE095
—
46,445,947.77————————————
494RR/RDA/11/25/12
Renovation of Chemmantheevu 4th Cross Street.
—
25,184,287.62————————————
495RR/RDA/10/25/12
Anaikoddai - Kakaithivu Road
—
34,361,480.40————————————
496RR/RDA/10/25/26
VC Road No 15
—
23,825,730.98————————————
497RR/RDA/12/25/06
Paalavinayagar road
—
17,373,382.99————————————
498RR/RDA/13/25/04
Suthanthirapuram Main Road Package 1
—
110,821,121.40————————————
499RR/RDA/11/25/17
Alakkatu Internal Road 5
—
25,141,870.23————————————
500RR/RDA/14/25/05
Kanakapuram school behind road
—
43,582,937.83————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 491–500 of 579 projects · page 50/58