Financial Dashboard

Monitor financial performance across 8 awarded projects

2026-11-05
03:04:50Live2026-11-05
0 / 8Advance Pendingpending advance projects / total projects
0 / 8IPC Pendingpending IPC projects / total projects
0 / 8Advance Paidadvance paid projects / total projects
0 / 8IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Kilinochchi · District

579Projects23,829.3Contract Mn
Kilinochchi 8 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn6808.7127.816% of contract681.0——————33.3%0.0%
Tender Below 50Mn00.0——————————
DL Stage 0100.0——————————
DL Stage 02143.632.073% of contract11.6——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
PIU1801.7—801.7——————0.0%0.0%
Kilinochchi81,654.1159.810% of contract1,494.3000.0000.025.0%0.0%
Tender Above 50Mn6 projects808.7Mn
16% paid127.8 Mn
Pending681.0Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 010 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project43.6Mn
73% paid32.0 Mn
Pending11.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU1 project801.7Mn
0% paid0.0 Mn
Pending801.7Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Kilinochchi8 projects1,654.1Mn
10% paid159.8 Mn
Pending1,494.3Mn
Planned Fin25.0%
Actual Fin0.0%

Avg Physical Progress per Province · Kilinochchi

Graphs reflect current view:8 awarded · Kilinochchi
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

161–170/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
161RR/RDA/25/24/02/SBP/RTP
Thundola Varathenna Road
Siri Construction
123,540,895.50————————————
162RR/RDA/25/24/03/SBP/RTP
From Thunaghahena To Temple Road
Siri Construction
20,065,425.82————————————
163RR/RDA/25/24/10/SBP/RTP
From Deniya kade Market to Henyaya Road Via Keenagahaella Road
Sam Dam
31,673,916.45————————————
164RR/RDA/24/25/21/SBP/RTP
Sudagala Grama Seva Division, From Sudagala to Tunudola Road up the mountain to …
DKS Construction
35,222,472.34————————————
165RR/RDA/24/25/34/SBP/RTP
Matuwagala Mudun Kotu Road
DKS Construction
—————————————
166RR/RDA/25/25/02/SBP/KGL
Elagapitiya Colany Road From Debathgama Pallebage to Tea Shakthi Praja Shalawa
EHL Constructions
36,210,751.61————————————
167RR/RDA/25/25/03/SBP/KGL
From Kehelpannala Junction to Pahala Kabawita Road
SF Constructions
71,786,959.20————————————
168RR/RDA/25/25/15/SBP/KGL
Moraliya Gagaboda Road
DHP Construction
38,093,328.62————————————
169RR/RDA/25/25/20/SBP/KGL
Neluwakkana gama meda Road
Loshitha Construction
23,823,804.13————————————
170RR/RDA/25/25/28/SBP/KGL
Naagas thenna Road
Jayasinghe Contractors (Pvt) Ltd.
102,000,742.36————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 161–170 of 218 projects · page 17/22