DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 11 awarded projects

2026-11-05
03:05:33Live2026-11-05
0 / 11Advance Pendingpending advance projects / total projects
0 / 11IPC Pendingpending IPC projects / total projects
0 / 11Advance Paidadvance paid projects / total projects
0 / 11IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Mullaitivu · EE: Mullaitivu · EE Office

11Projects1,090.6Contract Mn
Mullaitivu 11 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn7843.0260.131% of contract582.9——————85.7%0.0%
DL Stage 01146.428.862% of contract17.6——————0.0%0.0%
DL Stage 021110.891.783% of contract19.1——————100.0%0.0%
DL Stage 03163.943.067% of contract20.9——————100.0%0.0%
DL Stage 04126.415.960% of contract10.6——————0.0%0.0%
Mullaitivu111,090.6439.540% of contract651.1000.0000.072.7%0.0%
Tender Above 50Mn7 projects843.0Mn
31% paid260.1 Mn
Pending582.9Mn
Planned Fin85.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project46.4Mn
62% paid28.8 Mn
Pending17.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project110.8Mn
83% paid91.7 Mn
Pending19.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project63.9Mn
67% paid43.0 Mn
Pending20.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project26.4Mn
60% paid15.9 Mn
Pending10.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Mullaitivu11 projects1,090.6Mn
40% paid439.5 Mn
Pending651.1Mn
Planned Fin72.7%
Actual Fin0.0%

Avg Physical Progress per Province · Mullaitivu · EE: Mullaitivu

Project-wise Financials · Mullaitivu · EE: Mullaitivu (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Mullaitivu · EE: Mullaitivu (Mn · incl. VAT)

Scroll horizontally — 579 projects

Mullaitivu Division · Mullaitivu · EE: Mullaitivu (Mn · incl. VAT)

Mullaitivu District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:11 awarded · Mullaitivu · EE: Mullaitivu
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

461–470/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
461RR/RDA/21/25/28
Development of the road Sathutugama nidahas Mawatha Balance Section from the hou…
—
29,829,563.55————————————
462RR/RDA/20/25/19
Thalawa Tsunami junction to Indigaspathana road of Padeniya Anuradhapura Road
—
64,760,087.22————————————
463RR/RDA/20/25/23
Megichchawa Junction to Temple Road (Kulumeewakada Junction)
—
37,500,731.47————————————
464RR/RDA/20/26/23
First phase of Priman Mawatha via the by-road behind Kumbichchankulama tank
—
57,387,404.38————————————
465RR/RDA/21/25/25
School Main Road (Old Jumma Mosque Road)
—
43,759,842.36————————————
466RR/RDA/21/25/17
Hingurakgoda Samupakara Road to Bubula
—
174,553,300.63————————————
467RR/RDA/21/25/46
Girithale janapadaya pasal mawatha starting Section
—
22,545,305.56————————————
468RR/RDA/18/25/12
Anura Mahaththayalage niwase sita Nalalida dakwa kadurugaha ela dakwa margaya (G…
—
23,242,484.20————————————
469RR/RDA/18/25/05
158 Digana Grama niladari wasame 3 patumaga (vawa dakwa) (Yapahuwa)
—
11,774,916.28————————————
470RR/RDA/18/25/23
Horagasagara Nawarathna handiye sita Ihala kadigamuwa handiya dakwa margaya (Bin…
—
61,588,475.92————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 461–470 of 579 projects · page 47/58