DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-05
22:47:12Live2026-11-05
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
0 / 5Advance Paidadvance paid projects / total projects
0 / 5IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Uva Province · EE: Bandarawela · EE Office

567Projects20,718.2Contract Mn
Bandarawela 5 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn138.524.163% of contract14.4——————0.0%0.0%
Tender Below 50Mn218.95.831% of contract13.2——————0.0%0.0%
DL Stage 01115.114.596% of contract0.5——————100.0%0.0%
DL Stage 02113.115.4118% of contract-2.3——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Bandarawela585.659.870% of contract25.7000.0000.020.0%0.0%
Tender Above 50Mn1 project38.5Mn
63% paid24.1 Mn
Pending14.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn2 projects18.9Mn
31% paid5.8 Mn
Pending13.2Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project15.1Mn
96% paid14.5 Mn
Pending0.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project13.1Mn
118% paid15.4 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Bandarawela5 projects85.6Mn
70% paid59.8 Mn
Pending25.7Mn
Planned Fin20.0%
Actual Fin0.0%

Avg Physical Progress per Province · Uva Province · EE: Bandarawela

Project-wise Financials · Uva Province · EE: Bandarawela (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Uva Province · EE: Bandarawela (Mn · incl. VAT)

Scroll horizontally — 579 projects

Bandarawela Division · Uva Province · EE: Bandarawela (Mn · incl. VAT)

Badulla District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:5 awarded · Uva Province · EE: Bandarawela
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

311–320/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
311RR/RDA/25/25/03/SBP/KGL
From Kehelpannala Junction to Pahala Kabawita Road
SF Constructions
71,786,959.20————————————
312RR/RDA/25/25/05/SBP/KGL
Siyabalangamuwa Kudumbuwa Road
Shanho Engineering
39,262,197.06————————————
313RR/RDA/25/25/06/SBP/KGL
From Dombemada Post Office to Sillugala Via Wedollamada well
Shanho Engineering
37,416,631.86————————————
314RR/RDA/25/25/09/01/SBP/KGL
The first phase of the Matiyagane-Berawandare road from Mas Potha via Haliyagoda
Samindra construction
26,656,967.36————————————
315RR/RDA/25/25/09/02/SBP/KGL
The first phase of the Gaitahpura road via Ambagala on the Warakapola Technical …
—
—————————————
316RR/RDA/25/25/10/SBP/KGL
Elipangamuwa School Road through Pananawaththa
DHP Construction
23,988,665.80————————————
317RR/RDA/25/25/15/SBP/KGL
Moraliya Gagaboda Road
DHP Construction
38,093,328.62————————————
318RR/RDA/25/25/20/SBP/KGL
Neluwakkana gama meda Road
Loshitha Construction
23,823,804.13————————————
319RR/RDA/25/25/28/SBP/KGL
Naagas thenna Road
Jayasinghe Contractors (Pvt) Ltd.
102,000,742.36————————————
320RR/RDA/25/25/31/SBP/KGL
Developing the section connecting the road from the old office in Yatawala to th…
DHP Construction
13,369,909.30————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 311–320 of 579 projects · page 32/58