DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 0 awarded projects

2026-11-05
02:30:19Live2026-11-05
0 / 0Advance Pendingpending advance projects / total projects
0 / 0IPC Pendingpending IPC projects / total projects
0 / 0Advance Paidadvance paid projects / total projects
0 / 0IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

0%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · North Western Province · EE: Jaffna · EE Office

567Projects20,718.2Contract Mn
Jaffna 15 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn4329.053.516% of contract275.5——————75.0%0.0%
Tender Below 50Mn9155.591.859% of contract63.7——————100.0%0.0%
DL Stage 01135.337.1105% of contract-1.8——————100.0%0.0%
DL Stage 02134.419.055% of contract15.4——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Jaffna15554.1201.436% of contract352.8000.0000.093.3%0.0%
Tender Above 50Mn4 projects329.0Mn
16% paid53.5 Mn
Pending275.5Mn
Planned Fin75.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn9 projects155.5Mn
59% paid91.8 Mn
Pending63.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project35.3Mn
105% paid37.1 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project34.4Mn
55% paid19.0 Mn
Pending15.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Jaffna15 projects554.1Mn
36% paid201.4 Mn
Pending352.8Mn
Planned Fin93.3%
Actual Fin0.0%

Avg Physical Progress per Province · North Western Province · EE: Jaffna

No province data available

Awarded projects will appear here

Project-wise Financials · North Western Province · EE: Jaffna (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · North Western Province · EE: Jaffna (Mn · incl. VAT)

Scroll horizontally — 579 projects

Jaffna Division · North Western Province · EE: Jaffna (Mn · incl. VAT)

District District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:0 awarded · North Western Province · EE: Jaffna
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

101–110/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
101RR/RDA/17/25/14/EP/TRN
Amaithusha Road (School road to Vaithiyar road)
Shaniff Construction
5,006,100.00————————————
102RR/RDA/17/25/15/EP/TRN
Cemetery Road (Sajahan Mowlavi's house to Thajudeen shop)
Soyuru Sampath Construction & Suppliers
21,774,456.00————————————
103RR/RDA/17/25/16/EP/TRN
Valuvar Road (Main road to Kovil road)
Shaniff Construction
10,783,850.00————————————
104RR/RDA/17/25/18/EP/TRN
Sooranagar Main Road (Muththuchenai Junction to Thuvaraka Vithiyalayam)-Concrete
SSK Construction
25,155,240.00————————————
105RR/RDA/17/25/19/EP/TRN
Periya Suwami Kovil Road-Concrete
Motec Engineering & Construction
25,774,146.00————————————
106RR/RDA/SP/17/25/01/EP/TRN
Alankerny faisal Main Road (Koof Nagar)
NAS Construction
26,879,843.97————————————
107RR/RDA/SP/17/25/03/EP/TRN
Hajra Road (Alhira Jalaira Road)
STAAR Construction
38,692,742.00————————————
108RR/RDA/STAII/17/25/03/EP/TRN
From No.908 house to No.904 house road
Soyuru Sampath Construction & Suppliers
10,476,638.80————————————
109RR/RDA/STAII/17/25/04/EP/TRN
From No.851 house to Rajaela road
ARN Engineering & Construction
10,452,104.50————————————
110RR/RDA/17/25/10KM/01/EP/TRN
Road behind th hospital up to the morgue junction
Soyuru Sampath Construction & Suppliers
13,214,817.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 101–110 of 579 projects · page 11/58