DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 73 awarded projects

2026-11-05
16:57:03Live2026-11-05
0 / 73Advance Pendingpending advance projects / total projects
0 / 73IPC Pendingpending IPC projects / total projects
0 / 73Advance Paidadvance paid projects / total projects
0 / 73IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Eastern Province · Province

579Projects23,829.3Contract Mn
Eastern Province 73 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn6566.4152.027% of contract414.4——————96.9%0.0%
Tender Below 50Mn551,164.1376.332% of contract787.8——————41.8%0.0%
PIU00.0——————————
Tender Total611,730.5528.331% of contract1,202.2000.0000.047.2%0.0%
Direct LabourDL Stage 016311.7220.071% of contract91.7——————83.3%0.0%
DL Stage 02249.340.181% of contract9.2——————100.0%0.0%
DL Stage 03148.850.6104% of contract-1.8——————0.0%0.0%
DL Stage 04393.972.777% of contract21.3——————33.3%0.0%
Direct Labour Total12503.8383.476% of contract120.4000.0000.066.6%0.0%
—Eastern Province732,234.3911.741% of contract1,322.6000.0000.050.4%0.0%
Tender Above 50Mn6 projectsTender566.4Mn
27% paid152.0 Mn
Pending414.4Mn
Planned Fin96.9%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn55 projectsTender1,164.1Mn
32% paid376.3 Mn
Pending787.8Mn
Planned Fin41.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour311.7Mn
71% paid220.0 Mn
Pending91.7Mn
Planned Fin83.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projectsDirect Labour49.3Mn
81% paid40.1 Mn
Pending9.2Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 projectDirect Labour48.8Mn
104% paid50.6 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 043 projectsDirect Labour93.9Mn
77% paid72.7 Mn
Pending21.3Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Eastern Province73 projects2,234.3Mn
41% paid911.7 Mn
Pending1,322.6Mn
Planned Fin50.4%
Actual Fin0.0%

Avg Physical Progress per Province · Eastern Province

Graphs reflect current view:73 awarded · Eastern Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

271–280/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
271RR/RDA/11/25/11/NP/MNR
Eruvittan - Vellalakaddu Road
VN Construction JV
—————————————
272RR/RDA/11/25/05/NP/MNR
Konnayan Kudiyiruppu Internal Main Road
Sun Constructions (Pvt) Ltd.
90,000,000.00————————————
273RR/RDA/11/25/06/NP/MNR
Martin Road
Pastini Construction Material Supply
26,739,158.60————————————
274RR/RDA/11/25/09/NP/MNR
Renovation of Mathirikiramam internal Road Naruvilikulam
Abdul Cader Constructions
28,422,878.00————————————
275RR/RDA/11/25/10/NP/MNR
Malikaippiddy 1st 2nd 3rd 4th Road
Vision Lanka Engineering (Pvt) Ltd
22,726,000.00————————————
276RR/RDA/11/25/13/NP/MNR
Variveli Pandaraveli Road
Sanjeeve Construction Work
29,619,833.65————————————
277RR/RDA/11/25/14/NP/MNR
Pichaivanifa Nedunkulam Scheme Internal Road 2
Fahim Builders
14,944,097.22————————————
278RR/RDA/11/25/15/NP/MNR
Veppankulam Scheme Internal Road (Mosque) 3
Sanjeeve Construction Work
17,836,311.35————————————
279RR/RDA/11/25/16/NP/MNR
P.P.Potkerny Scheme Internal Road 1
Abdul Cader Constructions
14,295,963.00————————————
280RR/RDA/11/25/18/NP/MNR
Akaththimurippu Internal Road 3
Abdul Cader Constructions
15,815,393.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 271–280 of 579 projects · page 28/58