DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 55 awarded projects

2026-11-05
14:56:06Live2026-11-05
0 / 55Advance Pendingpending advance projects / total projects
0 / 55IPC Pendingpending IPC projects / total projects
0 / 55Advance Paidadvance paid projects / total projects
0 / 55IPCs PaidIPC paid projects / total projects
2,249.3 Mn

2,249.31 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

17.1%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Western Province · Province

579Projects23,829.3Contract Mn
Western Province 55 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn4207.010.45% of contract196.5——————0.0%0.0%
Tender Below 50Mn26391.794.824% of contract296.9——————30.8%0.0%
PIU1659.1—659.1——————0.0%0.0%
Tender Total311,257.7105.28% of contract1,152.5000.0000.025.8%0.0%
Direct LabourDL Stage 018211.8170.580% of contract41.4——————100.0%0.0%
DL Stage 02334.719.657% of contract15.0——————100.0%0.0%
DL Stage 03473.541.456% of contract32.1——————50.0%0.0%
DL Stage 049671.618.73% of contract653.0——————11.1%0.0%
Direct Labour Total24991.6250.125% of contract741.5000.0000.058.3%0.0%
—Western Province552,249.3355.416% of contract1,894.0000.0000.040.0%0.0%
Tender Above 50Mn4 projectsTender207.0Mn
5% paid10.4 Mn
Pending196.5Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn26 projectsTender391.7Mn
24% paid94.8 Mn
Pending296.9Mn
Planned Fin30.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU1 projectTender659.1Mn
0% paid0.0 Mn
Pending659.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 018 projectsDirect Labour211.8Mn
80% paid170.5 Mn
Pending41.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 023 projectsDirect Labour34.7Mn
57% paid19.6 Mn
Pending15.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 034 projectsDirect Labour73.5Mn
56% paid41.4 Mn
Pending32.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 049 projectsDirect Labour671.6Mn
3% paid18.7 Mn
Pending653.0Mn
Planned Fin11.1%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Western Province55 projects2,249.3Mn
16% paid355.4 Mn
Pending1,894.0Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Western Province

Graphs reflect current view:55 awarded · Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

391–400/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
391—
Udupila South Dolewatta
Creates Consultant and Construction
7,423,117.70————————————
392RR/RDA/02/25/18/WP/GAM
Peliyagoda Naranminiya Road
Ceylux Civil engineering (Pvt) Ltd
19,082,810.00————————————
393—
3 A road carpeted development near the Japanese Montessori at the junction of th…
Jeyanthan Construction
15,141,484.50————————————
394—
241 B Near Weliweriya North Suruwama Junction to Weliweriya Town
Yagoda Construction
11,473,274.80————————————
395—
Near Urapana Sisira Coir Mill to Hapugahagama Co-operative
Jeyanthan Construction
19,032,750.00————————————
396RR/RDA/03/25/02/WP/KTR
Concreting of the first side road on the left side of Rasik Road
Develco Engineering (PVT) LTD
7,705,537.20————————————
397RR/RDA/03/25/03/WP/KTR
Carpeting of Uswatta Lane
Ramano Engineers
6,059,612.50————————————
398RR/RDA/03/25/05/WP/KTR
From near Mr. Abeywardena's house on the Yawita Kammalgoda road block stones and…
Develco Engineering (PVT) LTD
21,827,299.85————————————
399RR/RDA/03/25/08/WP/KTR
Asphalting from near Valkandala transformer to Panthiya Watta (Malamiriskanda ro…
Accon Engineering (PVT) LTD
14,577,590.15————————————
400RR/RDA/03/25/09/WP/KTR
Concreting of Weedahena road
Develco Engineering (PVT) LTD
15,010,244.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 391–400 of 579 projects · page 40/58