DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 6 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:6 awarded · Northern Province · EE: Point Pedro
66.7%
0
On Progress
4 / 6 awarded
On Progress (incl. completed)4
RR/RDA/10/25/20/NP/JFNThuvali VeethyRR/RDA/10/25/213rd Cross StreetRR/RDA/10/25/26VC Road No 15RR/RDA/10/25/23Oorany Kudiyetta thidda Veethy
Click to filter the awarded table
0%
0
Delay
0 / 6 awarded
Delay0
No projects
Click to filter the awarded table
33.3%
0
Critical Delay
2 / 6 awarded
Critical Delay2
Click to filter the awarded table
66.7%
0
Completed
4 / 6 awarded
Completed4
RR/RDA/10/25/20/NP/JFNThuvali VeethyRR/RDA/10/25/213rd Cross StreetRR/RDA/10/25/26VC Road No 15RR/RDA/10/25/23Oorany Kudiyetta thidda Veethy
Click to filter the awarded table
Portfolio Breakdown · Northern Province · EE: Point Pedro · EE Office
Avg Physical Progress per EE Division · Northern Province · EE: Point Pedro
At-Risk Projects · Northern Province · EE: Point Pedro
Portfolio Timeline· 4 scheduled projects · Northern Province · EE: Point Pedro Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
4 projects
Filter awarded works
4 matching projects1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/10/25/20/NP/JFN | RR/RDA/10/25/20 | Thuvali Veethy | 100% | 32,948,293.95 | 47,624,825.22 | Awarded |
| 2 | RR/RDA/10/25/21 | — | 3rd Cross Street | 100% | 11,072,958.55 | 11,072,958.55 | Awarded |
| 3 | RR/RDA/10/25/26 | — | VC Road No 15 | 100% | 23,825,730.98 | 23,825,730.98 | Awarded |
| 4 | RR/RDA/10/25/23 | — | Oorany Kudiyetta thidda Veethy | 100% | 12,148,965.86 | 12,148,965.86 | Awarded |
Showing 1–4 of 4
Source: DRRRP • 6 projects • Data updated 2026-11-02 10:30 • 12:38:23 System live • Sri Lanka • 1 districts