DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 15 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:15 awarded · Hambantota

Portfolio Breakdown · Hambantota · District

579Awarded739Total
Hambantota 15 awarded of 15 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn0000%0.00.0————
Tender Below 50Mn550100%204.8153.6136.327.418% of contract89.0%59.5%
DL Stage 01330100%153.2153.2149.2102.767% of contract66.7%100.0%
DL Stage 02110100%37.737.737.729.779% of contract100.0%100.0%
DL Stage 03110100%127.6127.6127.689.070% of contract100.0%95.0%
DL Stage 04550100%325.0325.054.8184.957% of contract20.0%89.0%
PIU0000%0.00.0————
Not Specified0000%0.00.0————
Hambantota15150100%848.2797.0505.6433.754% of contract63.0%82.5%

Avg Physical Progress per EE Division · Hambantota

Portfolio Timeline· 13 scheduled projects · Hambantota Toggle
Portfolio · Awarded Works

Awarded Projects

3 projects

3/3 (filtered)

Filter awarded works

3 matching projects1 active

ActiveDelay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/09/25/08/SP/HMBRR/RDA/09/25/08
Carpeting Pissubedda Medagamgoda road
98%
28,923,336.7546,881,232.95Awarded
2RR/RDA/08/25/05—
Koggalla bus stand to Sooriyawewa Road
95%
127,573,213.52127,573,213.52Awarded
3RR/RDA/09/25/07—
Carpeting Dabewelena Gravel Road
98%
54,766,473.9554,766,473.95Awarded
Showing 1–3 of 3
Per page:
Source: DRRRP • 15 projects • Data updated 2026-11-02 10:30 • 11:39:17