DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/18/25/NWP/KRG/10

Uyandana Yaggapitiya

KurunegalaNorth Western ProvinceKurunegalaDivisional SecretariatSenerath Engineering (pvt) LtdContractorLKR 45,801,928.20Contract Sum154 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-11-20
Completed
Possession
–
Pending
Commencement
2025-12-04
Completed
Scheduled Completion
2026-03-03
Completed
Anticipated Completion Date
2026-05-07
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionKurunegala
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/107
Tender ByProcurement Division