DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/12/25/57/NP/VVN

Nikawewa Right to Sapumalthanna

VavuniyaNorthern ProvinceVavuniyaDivisional SecretariatYansika ConstructionContractorLKR 11,848,115.95Contract Sum0 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-24
Completed
Possession
–
Pending
Commencement
2025-11-07
Completed
Scheduled Completion
2026-02-05
Completed
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorthern Province
DistrictVavuniya
DS Division-
GN Division-
Electorate-
PD RegionNorthern Province
CE RegionVavuniya
EE DivisionVavuniya
Authority Tier-
Authority Name-
Package No.RR/RDA/12/25/57
Tender ByProvincial Director