DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/07/25/11/SP/GAL

Elathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet Kirima

GalleSouthern ProvinceGalleDivisional SecretariatJayathissa ConstructionContractorLKR 20,801,618.20Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-09-09
Completed
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2025-12-29
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictGalle
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionGalle
EE DivisionGalle
Authority Tier-
Authority Name-
Package No.RR/RDA/07/25/11
Tender ByProvincial Director