DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/08/25/19/SP/MTR

Sahakara wathu Adikari nila niwasa asala sita koppara weediya pittaniya dakwa margaya Sanwardanaya kirima

MataraSouthern ProvinceDeniyayaDivisional SecretariatGamage BuildersContractorLKR 10,371,473.20Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-09-22
Completed
Possession
–
Pending
Commencement
2025-10-06
Completed
Scheduled Completion
2026-01-05
Completed
Anticipated Completion Date
2025-12-16
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionDeniyaya
Authority Tier-
Authority Name-
Package No.RR/RDA/08/25/19
Tender ByProvincial Director