DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/22/25/04/UP/BDL

Buluwa Margaya

BadullaUva ProvinceMahiyanganayaDivisional SecretariatSamadhi ConstructionContractorLKR 19,800,000.00Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-23
Completed
Possession
–
Pending
Commencement
2025-11-06
Completed
Scheduled Completion
2026-02-05
Completed
Anticipated Completion Date
–
Pending