DRRRP Awarded Dl DL Stage 03

RR/RDA/06/25/43

Development of Ponnagar Road

Nuwara EliyaCentral ProvinceNorwoodDivisional Secretariat-ContractorLKR 37,481,052.81Contract Sum75 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-17
Completed
Scheduled Completion
2025-11-30
Completed
Anticipated Completion Date
2026-01-31
Completed