DRRRP Awarded Dl DL Stage 01

RR/RDA/16/25/05

Jannah Road from Annor Road to Jannah Mosque Junction

AmparaEastern ProvinceAkkaraipattuDivisional Secretariat-ContractorLKR 15,746,511.36Contract Sum62 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-08-21
Completed
Anticipated Completion Date
2025-09-30
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceEastern Province
DistrictAmpara
DS Division-
GN Division-
Electorate-
PD RegionEastern Province (Akkaraipattu)
CE RegionAkkaraipattu
EE DivisionAkkaraipattu
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Pallikkudiyiruppu-02